https://www.miningweekly.com

Continental Gold intensifies focus on Buriticá advancement

12th March 2018

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

     

Font size: - +

JOHANNESBURG (miningweekly.com) – TSX-listed Continental Gold will focus on completing detail engineering and finalising major mill and infrastructure procurement in the year ahead, to advance its Buriticá project, in Colombia, to its first gold pour in 2020.

“We want to be well advanced with both earthworks and concrete work; start plant equipment mechanical and piping installations; begin required site infrastructure construction, including warehouse, mine rescue, change house, assay lab and ancillary buildings; and start tailings storage facilities construction and aerial tramway installation to be used for delivering filtered tailing to the paste plant,” the company said in a statement on Friday.

It would further seek to advance underground mine development initiatives, including Yaraguá and Veta Sur ramps, stope definition drilling, and sublevel development in initial production areas; start construction of the 32 km 110 kV transmission line to provide power from the national grid; and continue with infill drilling into broad mineralised zones (BMZ) and for increasing drill density to upgrade tonnes and ounces in the current mineral resource into higher confidence categories.

Continental would also focus on step-out drilling extensions to identify potential resource along strike and down dip and exploration drilling on newly identified greenfield targets.

“Major milestones were reached during 2017 on the advancement of our Buriticá project. After receiving our environmental permit in late 2016, we secured $275-million of project debt financing with Red Kite, a strategic investment of $109-million from Newmont and initiated construction of the largest gold mine in Colombia.

“Underground development is advancing on three separate headings and earthworks in the Higabra Valley is moving rapidly towards first major concrete pour in the coming weeks.

“We are also excited to have resumed drilling at the Buriticá project after a multiyear hiatus and look forward to both improving the mineral resource estimate with definition and infill drilling and testing newly generated brownfield and greenfield targets with a goal of identifying a new discovery in 2018,” said CEO Ari Sussman.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (12/04/2024)
12th April 2024 By: Martin Creamer
Magazine round up | 12 April 2024
Magazine round up | 12 April 2024
12th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.158 0.193s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: