Sibanye-Stillwater says operational recovery progressing well
JSE-listed gold and platinum group metals (PGMs) miner Sibanye-Stillwater says its operational recovery from the severe Covid-19-induced lockdown in South Africa has progressed well to date.
The build-up to normalised production levels at the miner’s South African operations has progressed “better than planned” and the manner in which employees have been reintegrated into the operations without a notable increase in infection rates or operational disruptions, validates the more gradual recall and production build-up strategy, it states.
In terms of returning workforces, Sibanye notes that, by the end of the third quarter, its domestic gold operations had recalled about 92% of the workforce and achieved a production run rate of about 99% of planned levels.
In terms of the South African PGM operations, these managed to recall about 88% of the workforce with a production run rate of 93% of planned levels achieved.
By mid-October, both the South African gold and PGM operations were operating at close to planned production rates, with the employee complement close to pre-Covid-19 levels.
However, while the US PGM operations have continued to operate throughout the year, Covid-19 protocols (particularly compliance with physical distancing requirements) has had an ongoing negative impact on productivity, the miner points out.
The physical distancing impact is most prevalent on transport to and from work, with employees living throughout the state of Montana and travelling longer distances to work than is the case for employees in South Africa.
As a result, restricted access to the operations also affected shift arrangements and blasting schedules, resulting in a negative 8% impact on productivity during the third quarter.
HEALTH & SAFETY
The safe production performance for the third quarter was mixed, with another good quarterly safety performance from the South African PGM operations, offset by a decline in the safety performance of the domestic gold operations.
The local PGM operations delivered another fatality-free quarter (mirroring the zero fatalities for the second quarter), relative to two fatalities experienced in the third quarter of 2019.
As such, on October 13, the South African PGM operations achieved a milestone of four-million fatality-free shifts, with the last fatality recorded at the Siphumelele shaft in March.
However, to the miner’s regret, after over 13-million shifts and almost two years without any fatal incidents, the South African gold operations suffered two fatalities during the third quarter.
“Despite these fatalities we believe that our safety strategy remains appropriate and we will continue to work towards our goal of zero harm,” Sibanye says.
In terms of lost-time injury frequency rates, the miner reports an improvement in the serious injury frequency rate, the lost day injury frequency rate and the total injury frequency rates of 12%, 20% and 23%, respectively, being achieved in the third quarter, compared with the same period in 2019 for the South African gold operations.
PGM OPERATIONS
In the US, Sibanye’s mined two-element PGMs production for the quarter was 147 835 oz.
In South Africa, four-element (4E) PGMs production reached 427 715 oz for the third quarter – 18% lower than for the comparable period in 2019, primarily as a result of the progressive production build-up during the quarter.
Costs were well managed with all-in sustaining costs having increased by only 5% year-on-year to R16 985/oz of 4E, despite lower production and above inflation electricity tariffs and wage adjustments.
GOLD OPERATIONS
The miner’s gold operations experienced a smooth and ahead-of-plan production build-up during the third quarter, with gold production of 288 938 oz.
Gold production, excluding DRDGold, totalled 240 262 oz, which was similar to the comparable period in 2019.
All-in sustaining costs for the third quarter were R715 345/kg, which remained elevated as a result of lower production and above inflation electricity tariff and wage increases.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation