Semafo hits 97% completion at Boungou, expects first gold by June

17th May 2018

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – Montreal-based miner Semafo reports that construction of its $231-million Boungou mine, in Burkina Faso, is 97% complete.

Commissioning of the process plant is under way, with the first ore scheduled to be introduced to the mill circuit by month-end, the West Africa-focused miner said on Thursday.

The first gold pour is now pencilled in for June, slightly ahead of schedule.

Semafo said construction of the processing plant is now 100% complete, with commissioning nearing the 60% level.

The crushing circuit, vertimill, pre-leach and tailings thickeners, leaching/carbon-in-pulp circuit and water services are already commissioned and commissioning of the semi-autogenous grinding mill, gravity, elution circuit, gold room, compressors and oxygen plant started earlier this month.

About $202-million of the construction budget has been spent to date.

Further, Semafo said pre-stripping is 87% complete, with 15.6-million of the projected 18-million tonnes extracted. The company has already amassed a stockpile of 70 000 t of low-grade ore on the run-of-mine pad.

Meanwhile, mine operator recruitment and training is nearing the end this month. Eighty-six per cent of the 1 480 personnel, including contractors, have been employed.

The company has now initiated the demobilisation of construction and contract personnel, having worked 515 days without a single lost-time injury.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.174 0.209s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: