Hualilan gold project, Argentina

Photo by Challenger Gold
Name of the Project
Hualilan gold project.
Location
Department of Ullum, San Juan province, Argentina.
Project Owner/s
Challenger Gold, through Golden Mining and related project entities.
Project Description
A prefeasibility study published in May 2026, has determined that Hualilan can be developed as a conventional truck-and-shovel openpit mine with on-site processing.
The selected development concept includes a 1.5-million-tonne-a-year process plant incorporating crushing, grinding, flotation, leaching and doré production, and an eight-million-tonne-a-year heap-leach facility, designed to treat suitable ore through modular crushing and leaching.
This dual-stream approach allows for ore to be routed according to value, metallurgy and overall project economics, consequently improving flexibility and supporting a more resilient operating strategy.
Life-of-mine production is estimated at 1.84-million ounces of gold equivalent over 14.25 years.
The project forecasts production of more than 105 000 oz/y gold equivalent in Year 1 and 2, followed by 12 years of production averaging 135 000 oz/y gold equivalent.
Potential Job Creation
The project is expected to create 900 new jobs.
Net Present Value/Internal Rate of Return
Using a $3 500/oz gold price, the project has a net present value, at a 5% discount rate, of $1.45-billion and an internal rate of return of 45%, with a payback of 2.25 years.
Capital Expenditure
$232-million.
Planned Start/End Date
Not stated.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
None disclosed.
Contact Details for Project Information
Challenger Gold, tel +61 8 6385 2743 or email admin@challengergold.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation