All three components of R16bn Koruson 2 renewables cluster now operational
All three projects that make up Envusa Energy’s giant 520 MW Koruson 2 renewable-energy cluster are now officially operational, after 130 MW of the 140 MW Hartebeesthoek Wind Farm entered into commercial operation.
The residual 10 MW is scheduled to come online in September.
The R16-billion cluster, built on sites in the Eastern and Northern Cape provinces, includes the two 140 MW-apiece wind farms of Umsobomvu and Hartebeesthoek, as well as the 240 MW Mooi Plaats Solar PV facility.
All told, the cluster comprises some 50 wind turbines, 420 000 solar panels and 943 string inverters.
The electricity generated is being wheeled into the national grid and has been contracted by Envusa Energy, which is also a licensed electricity trader, to supply the operations of Valterra Platinum, Kumba Iron Ore and De Beers.
CEO Nicole Mason says the Koruson 2 cluster has proved that the commercial model implemented by Envusa Energy, formed in 2022 by Anglo American and EDF power solutions, can be delivered at scale.
The model involves multiple renewables generators supplying multiple industrial customers through a licensed electricity trader, while using the National Transmission Company South Africa’s transmission network.
The company, she adds, is currently advancing with its next tranche of wind projects that have a 340 MW combined capacity, with financial close targeted for the first quarter of 2027 and commercial operations in 2029.
Envusa Energy aims to develop between 3 GW and 5 GW of wind, solar and battery storage capacity across Southern Africa by 2030, she reports.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation