Meridian confirms $2.09bn value of Cabaçal project even at base case prices
London-and Toronto-listed Meridian Mining has confirmed a net present value (after tax) of $2.09-billion for the Cabaçal project in Brazil, even at base case prices of $3 570/oz of gold, $5.03/lb of copper and $50.17/oz of silver.
Having published a definitive feasibility study (DFS) on the project on September 22, Meridian says the project can deliver an internal rate of return of 108% and has a payback period of ten months.
In a spot price scenario of $ 4 394/oz gold, $6.53/lb copper and $64.14/oz silver, the project's NPV increases to $2.9-billion, the IRR widens to 134% and the payback period reduces to eight months.
The DFS confirms Cabaçal can viably produce 183 526 gold-equivalent ounces a year over the first five years, at an all-in sustaining cost of $1 056/oz, for an initial capital investment of $322-million.
The project is expected to generate free cashflow (after tax) of $2.9-billion over its 14-year lifetime.
"Our NPV-to-capital expenditure ratio of 6.5 times is a testament to the compelling economic potential of the Cabaçal project. Using spot prices these all get better again. Reading these numbers, it elevates Cabaçal to potentially be the next “near-term” volcanogenic massive sulphide gold/copper mine developed globally.
"Importantly, the study is based on a conservatively engineered mine design, that can be financed and built," says CEO Gilbert Clark.
He confirms that pre-construction investments are already underway with committed capital contracts of $15.9-million, while installation licence permitting and financing activities for construction are progressing.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation