Makuutu rare earths project, South Africa – update

Image of drill core from the Makuutu project

Photo by Ionic Rare Earths

7th August 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Makuutu rare earths project.

Location
Uganda, 120 km east of Kampala.

Project Owner/s
Ugandan company Rwenzori Rare Metals (RRM) owns 100% of the project and Ionic Rare Earths (IonicRE) owns 60% of RRM. IonicRE has signed a conditional share purchase agreement to acquire a further 34% interest, which would increase its ownership to 94% on completion.

Project Description
The Stage 1 definitive feasibility study (DFS) proposes an openpit mining operation at an annualised mining rate of five-million tonnes a year of mineralisation for total rare-earth oxide (TREO) equivalent production of 40 090 t.

The maiden ore reserve for Stage 1 over retention licence 1693 is 172.9-million tonnes grading 848 parts per million (ppm) TREO for 146 654 t of contained TREO.

Stage 1 envisages production of 1 300 t/y of rare earths in the first ten years, averaging 1 156 t/y over the estimated 35-year mine life.

The broader deposit comprises nine licences covering about 300 km². It has a mineral resource of 617-million tonnes grading 630 ppm TREO comprising 517-million indicated tonnes and 99-million inferred tonnes. Its product basket comprises about 45% heavy rare earths and includes neodymium, praseodymium, dysprosium and terbium. A mining licence for the central tenement was awarded in January 2024, and the demonstration plant produced its first mixed rare-earth carbonate during the March 2024 quarter.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $406-million and internal rate of return of 32.7%, with a payback of about three years.

Capital Expenditure
The project has an initial capital expenditure of $120.8-million.

Planned Start/End Date
No revised final investment decision or first-production date has been announced. The strategic review is intended to assess options to enhance value and accelerate development.

Latest Developments
On July 31, 2026, IonicRE, through RRM, launched a strategic review of Makuutu following interest from the US and other Western-aligned stakeholders. 

The review will consider strategic, structural and funding alternatives, including strategic or government-backed partners, new investment structures and possible listings in other jurisdictions. No decision has been made and IonicRE has cautioned that the review might not result in a transaction or ownership change.

Makuutu is a member of the Forum on Resource Geostrategic Engagement, formerly the Minerals Security Partnership. IonicRE says the project’s mixed rare-earth carbonate product is not committed to China and could provide a long-term source of magnet and heavy rare earths for Western markets.

Key Contracts, Suppliers and Consultants
RRM (installation contract); and DRA Global (DFS review).

Contact Details for Project Information
IonicRE, tel +61 3 9776 3434 or email investors@ionicre.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

This week: Anglo highlights ability to provide capital efficient copper growth in tightening market; Valterra Platinum remains ‘highly confident’ in ‘robust outlook’ for PGM demand and, Decarbonisation reinforcing demand for Kumba Iron Ore‘s high grade, lump products
Resources Watch
5th August 2026
Glencore CEO Gary Nagle.
Glencore half-year earnings up 86% to $10bn
5th August 2026 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.059 0.095s - 117pq - 2rq
Subscribe Now