https://www.miningweekly.com
DRDGOLD|Sibanye-Stillwater|South Africa|Driefontein 2 Plant|Far West Gold Recoveries|Libanon|Gold|Gold Mining|Job Creation|Mineral Reserves|Tailings Retreatment|Gauteng|West Rand
|||||
drdgold|sibanye-stillwater-company|south-africa|driefontein-2-plant|far-west-gold-recoveries|libanon|gold|gold-mining|job-creation|mineral-reserves|tailings-retreatment|gauteng|west-rand

Far West Gold Recoveries operation, South Africa – update

Image of FWGR shaft

Photo by DRDGOLD

4th September 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Far West Gold Recoveries (FWGR) operation.

Location
Gauteng, South Africa.

Project Owner/s
FWGR is owned and operated by DRDGOLD. Sibanye-Stillwater holds a 50.1% controlling interest in DRDGOLD.

Project Description
FWGR is a surface gold-retreatment operation that treats historic tailings in the West Rand goldfields. The operation is being expanded through DRDGOLD's Vision 2028 programme.

Phase 1 included upgrading the Driefontein 2 plant (DP2) to process tailings from the Driefontein 5 dump at between 400 000 t and 600 000 t a month and depositing the residue on the upgraded Driefontein 4 tailings dam.

The current expansion comprises the DP2 plant expansion, a regional tailings storage facility (RTSF) and a 135 km pipeline network linking DP2, the RTSF and the 74.3-million-tonne Libanon dump.

The expanded DP2 plant is designed to increase FWGR throughput from about 500 000 t a month to 1.2-million tonnes a month. Once operating, the Libanon reclamation station is planned to contribute 600 000 t a month.

The 800 ha, fully lined RTSF is designed initially to receive 1.2-million tonnes a month, with capacity to increase to 2.4-million tonnes a month and ultimately store up to 800-million tonnes of tailings.

Following the transfer of the Kloof 2 dump from Sibanye-Stillwater to FWGR in December 2025, 67-million tonnes were added to DRDGOLD's mineral reserves, extending FWGR's life-of-mine (LoM) by four years. Sibanye-Stillwater reports an FWGR LoM to 2045.

Potential Job Creation
Since its inception, FWGR has secured employment for more than 150 employees. Further opportunities are expected as the Vision 2028 expansion is implemented.

Capital Expenditure
DRDGOLD invested R330-million in Phase 1.

Vision 2028 capital allocated to FWGR comprises about R1.9-billion for the DP2 expansion, R3.4-billion for the RTSF and R1.2-billion for the pipeline project. DRDGOLD has also committed R880-million to an up-flow reactor at FWGR.

Planned Start/End Date
Phase 1 commercial production started on April 1, 2019.

Completion of the expanded DP2 plant is now expected in the second quarter of the 2027 financial year. Following completion and once beneficial occupation of the RTSF has been obtained, Libanon is planned to add 600 000 t a month, increasing FWGR throughput to 1.2-million tonnes a month.

Latest Developments
The expanded DP2 plant's new elution circuit and smelt house were commissioned on July 14, 2026, with first gold poured on the same day.

At June 30, 2026, construction of the RTSF was about 67% complete and the pipeline network linking DP2, the RTSF and Libanon was about 95% complete.

The water-use licence for the Libanon reclamation pumpstation was approved in July 2026, allowing for the construction of the pumpstation to proceed and clearing a key regulatory constraint on completion of the final link in the pipeline network.

DRDGOLD's wider Vision 2028 programme is an estimated R10-billion investment to increase combined throughput at Ergo and FWGR, and lift yearly gold production towards six tonnes by 2028. More than R5-billion had been invested across the programme by August 2026.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
DRDGOLD, tel +27 11 470 2600.
Third Act Consulting, on behalf of DRDGOLD, email DRDGOLD_Communications@thirdactconsultants.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

ARM CEO Phillip Tobias.
ARM headline earnings up 19%, dividend declared
4th September 2026 By: Martin Creamer
Photo of Martin Creamer
On-The-Air (04/09/2026)
4th September 2026 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.054 0.088s - 117pq - 2rq
Subscribe Now