Crawford nickel sulphide project, Canada – update

Image of periodic table symbol for nickel

16th October 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Crawford nickel sulphide project.

Location
Timmins, in Ontario, Canada.

Project Owner/s
Nickel focused exploration company Canada Nickel Company.

Project Description
The Crawford project will be a large-scale producer of critical minerals, including nickel and cobalt.

The operation will produce 83-million pounds (38 000 t/y) of nickel a year over a 41-year life, with production of 48 000 t/y nickel, 800 t/y of cobalt, 13 000 oz/y of palladium and platinum, 1.6-million tonnes a year of iron and 76 000 t/y of chrome over its 27-year peak period.

The first phase of the project will have a throughput of 60 000 t/d.

The second phase, planned for commissioning during the fourth year, will double mill throughput to 120 000 t/d.

The project is designed to incorporate Canada Nickel’s in-process tailings carbonation technology, which has demonstrated the potential to store 1.5-million tonnes of carbon dioxide a year at peak production. Crawford is also expected to be North America’s only primary source of chromium.

Potential Job Creation
An independent economic-impact study estimates that Crawford could support about 185 000 person-years of employment and contribute about C$70-billion to Canada’s gross domestic product over the mine life.

Net Present Value/Internal Rate of Return
The project has an estimated after-tax net present value (NPV) of $2.8-billion and an internal rate of return (IRR) of 17.6%. Including expected carbon capture, utilisation and storage tax credits, the after-tax NPV increases to $2.9-billion and the IRR to 18.9%.

Capital Expenditure
Front-end engineering design, completed in 2024, increased the initial capital cost by about 5%, to $2-billion.

Planned Start/End Date
Canada Nickel is targeting a construction decision in 2027. Detailed engineering, project financing and the remaining provincial and federal permits are being advanced ahead of planned construction.

Latest Developments
All primary approvals needed for the Stage 1 development are now in place, enabling the company to advance from permitting to project execution.

Cavalier will now continue site preparation activities, build out the personnel needed for development and work towards finalising project funding.

Key Contracts, Suppliers and Consultants
Ausenco Engineering Canada (PEA and front-end engineering design); and SSH Mining (mining contractor).

Contact Details for Project Information
Canada Nickel Company, email info@canadanickel.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 
Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 16 October 2026
Magazine round up | 16 October 2026
16th October 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

➕

➕

➕

➕

➕

RESEARCH CHANNEL AFRICA

SUBSCRIBE

➕

➕

➕

➕

➕

➕

➕

➕

➕

➕

CORPORATE PACKAGES

CLICK FOR A QUOTATION

➕

➕







sq:0.043 0.072s - 117pq - 2rq
Subscribe Now