Burnstone gold project, South Africa – update

Underground mining at the Burnstone gold project

Photo by ©Creamer Media

4th September 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Burnstone gold project.

Location
Near Balfour, Mpumalanga, South Africa.

Project Owner/s
Multinational Sibanye-Stillwater.

Project Description
The shallow, advanced underground gold development project will mine the Kimberley reef at an average depth of about 550 m and a maximum planned depth of about 1 050 m.

Existing infrastructure includes a functional metallurgical plant and tailings storage facility; equipped vertical and decline shafts; a trackless decline; surface infrastructure, including offices, workshops and compressors; and extensive underground development and infrastructure.

The current development plan envisages a 25-year mine life and average steady-state gold production of about 130 000 oz/y. Gold production is expected to build progressively towards steady-state output.

As at December 31, 2025, Burnstone contained surface and underground gold mineral reserves of 2.7-million ounces and mineral resources of 8.9-million ounces.

Potential Job Creation
The project is expected to build up to about 2 500 employees and contractors at steady-state operations.

Net Present Value/Internal Rate of Return
The restated feasibility study estimates a net present value of about R19.2-billion at a 10% discount rate and an internal rate of return of about 36.1%, in 2026 real terms.

Capital Expenditure
Project infrastructure capital is estimated at about R3.5-billion over six years, including about R2.5-billion of preproduction capital until 2028. A R98-million project budget has been approved for 2026.

Planned Start/End Date
Preproduction capital expenditure is planned for 2027 and 2028, with the processing plant expected to start operating in 2029. 

Latest Developments
Sibanye-Stillwater reported in its 2026 half-year results that the project had received a positive investment decision from the board following completion of a restated feasibility study and in-house assurance review. 

Project setup has started, supported by the approved R98-million 2026 budget.

The decision reverses the previous deferral of the project and positions Burnstone as a near-term growth project intended to support the transition of Sibanye-Stillwater's South African gold portfolio towards shallower, lower-risk and longer-life production.

Burnstone's existing mining right is valid until February 16, 2027.

Key Contracts, Suppliers and Consultants
Read, Swatman & Voigt, or RSV (engineering design team for the balance of the engineering design); DLC Town Plan (access surveying and registration of the new servitudes for the new access road to Burnstone); and DTS (design change to remove the skips from the shaft using the rock winder bank area).

Contact Details for Project Information
Sibanye-Stillwater investor relations, tel +27 11 278 9600 or email ir@sibanyestillwater.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Latest News

Kazera subsidiary receives Northern Cape mining right approval
Kazera subsidiary receives Northern Cape mining right approval
2nd September 2026 By: Sabrina Jardim

Showroom

Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 
Trotech
Trotech

Design, Construction and Maintenance of Site Erected, Welded Bulk Storage Tanks for the Petrochemical, LNG, Ammonia and Sustainable fuel Sectors.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mount Lyell copper/gold/silver project in Tasmania.
Two new projects win Sibanye-Stillwater thumbs up
2nd September 2026 By: Martin Creamer
Resources Watch
Resources Watch
2nd September 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.029 0.062s - 117pq - 2rq
Subscribe Now