First Tin|Taronga Tin Project|Mining|Tin|Bill Scotting|New South Wales
||||
first-tin|taronga-tin-project|mining|tin|bill-scotting|new-south-wales

Australia-focused First Tin undertakes optimised DFS based on increased ore reserves at Taronga

13th August 2026

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

London-listed First Tin finds in an updated ore reserve statement on the Taronga tin project, in New South Wales, an increase of five-million tonnes of tin to 45-million tonnes grading 0.12%, containing about 55 000 t of tin, in proved and probable ore reserves.

Proven ore reserves increased by 19% from 26-million tonnes grading 0.14% tin to 31-million tonnes grading 0.13% tin, for 41 000 t of contained tin.

The updated ore reserves are contained entirely within the existing pit limits that form the basis of First Tin's current permitting process, and add about one year to the current mine life.

The company says preliminary pit optimisation using the recently updated mineral resource estimate suggest potential for about 20-million tonnes of additional mill feed and about four years of additional mine life under an optimised scenario - based solely on measured and indicated resources, subject to detailed pit designs, scheduling studies and permitting.

The preliminary pit optimisation study indicates that the pit could extend between 25 m and 50 m deeper than the current pit design envisioned in the definitive feasibility study (DFS) on the Taronga project.

First Tin CEO Bill Scotting says the updated ore reserve statement represents an important step forward for the Taronga project, since the increased proved and probable ore reserves by 13% to 45-million tonnes adds one year to the current mine plan, all within existing pit limits being assessed through the permitting process.

"The combination of increased ore reserves, a lower strip ratio and the potential for a materially longer mine life provides further support for the development of Taronga. We look forward to incorporating this potential upside into the forthcoming optimised DFS."

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Projects

Showroom

Energy and Densification Systems
Energy and Densification Systems

Energy and Densification Systems (EDS) has developed equipment for crushing, milling, blending and densifying products. Based on its globally...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mount Lyell copper/gold/silver project in Tasmania.
Two new projects win Sibanye-Stillwater thumbs up
2nd September 2026 By: Martin Creamer
Resources Watch
Resources Watch
2nd September 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.052 0.074s - 139pq - 2rq
Subscribe Now