Tulu Kapi gold project, Ethiopia – update

Photo by KEFI Gold and Copper
Name of the Project
Tulu Kapi gold project.
Location
Western Ethiopia.
Project Owner/s
London-listed KEFI Gold and Copper (formerly KEFI Minerals) will own 80% of the exploration and holding company for the government of Ethiopia, KME, which, in turn, will own 56% of Tulu Kapi Gold Mines Share Company (TKGM), thus bestowing KEFI with a 45% beneficial interest in the project.
Project Description
Tulu Kapi has an ore reserve estimate of 15.4-million tonnes at 2.1 g/t gold for 1.1-million ounces of gold.
Openpit gold production is estimated at 140 000 oz/y over a seven-year mine life.
Total life-of-mine production is estimated at 980 000 oz.
The conventional openpit mining operation will include a carbon-in-leach processing plant. The mine will be connected to Ethiopia’s electricity grid through a new, 47-km-long, 132 kV dedicated power line relatively close to the country’s major hydropower-generation source. An emergency diesel power plant will also be installed to provide emergency backup power for critical process equipment in the event of grid power failure.
An updated standalone preliminary economic assessment (PEA) supports detailed planning for the Tulu Kapi underground mine. The preliminary mining inventory comprises 2.38-million tonnes at 3.3 g/t gold containing about 253 000 oz. Underground ore is expected to be blended with openpit feed, lifting combined steady-state production to about 180 000 oz/y and contributing about 237 000 oz of recovered gold. The PEA includes inferred resources and does not constitute an ore reserve; there is no certainty that its outcomes will be realised.
Potential Job Creation
The project is expected to create about 1 000 direct jobs and 5 000 to 10 000 indirect jobs, with foreign direct investment of about $500-million, including historical investment.
Net Present Value/Internal Rate of Return
At gold prices of between $3 000/oz and $5 000/oz, the net present value (NPV) of Tulu Kapi at the start of construction is between $710-million and $1.6-billion.
Once in production, Tulu Kapi is set to generate between $1.9-billion and $3.6-billion of net operating capital over seven years, or between $284-million and $526-million a year. This equates to an internal rate of return (IRR) of between 112% and 200%.
On a standalone incremental basis and at an assumed gold price of $2 350/oz, the 2026 underground PEA estimates an after-tax NPV, at a 5% discount rate, of about $274.1-million, an IRR of 220% and payback of nine months.
Capital Expenditure
KEFI expects the full development to cost $340-million. The total project cost is about $500-million after taking into account that the mining contractor finances the mining fleet of $60-million and historical expenditure is more than $100-million.
Preproduction development capital for the underground mine is estimated at $8.09-million, with a maximum cash drawdown of about $10.5-million. The expenditure is expected to be funded from openpit operating cash flow, with no new equity assumed.
Planned Start/End Date
Before the September 2026 suspension, openpit production was targeted for mid-2028. Underground engineering was scheduled for completion in the fourth quarter of 2027, decline development and trial production for 2028, and first stope ore and ramp-up for 2029. It is too early to assess what impact the suspension may have on the development timetable.
Latest Developments
KEFI Gold and Copper is restarting development after suspending work on September 7, following a serious safety incident on September 4.
The suspension has been lifted after detailed reviews and consultations.
The incident was concluded on September 10, which KEFI has attributed largely to collaboration with the local community.
Since then, the company’s senior management and its local management team have held detailed consultations with community representatives, the leaders at all levels of the Ethiopian and Oromia governments and their relevant agencies, along with other stakeholders in Ethiopia. The company has pointed out that these discussions have particularly focused on local community, localisation of operational activities and security arrangements.
As a result of these “positive” discussions, KEFI is now restarting the development programme in a phased and measured approach.
Construction is restarting for electricity connection infrastructure and remobilising for the construction of new access roads. This will be followed by replacing housing and lands for community members resettling from the mining licence area.
This will allow for the initial construction – entailing the installation of planned security infrastructure, bulk earthworks (for the processing factory and other infrastructure to be delivered and installed) and construction of the permanent accommodation facilities for the workforce – on the mining licence area.
With its international mining specialist staff and contractors, Kefi is prioritising the localisation of fieldwork to strong local firms that have successful records in the region around Tulu Kapi.
The company has highlighted that its lenders have continued to show their support for the company and the development of the project during ongoing discussions with regard to updating the development sequencing and the associated drawdown of funds.
KEFI has said it is encouraged by the expressions of interest to increase the already strong support from Ethiopian stakeholders, including the local investment and construction sectors.
Key Contractors, Suppliers and Consultants
Principal contractors: Lycopodium (process plant design and construction); PW Mining; the Ethiopian Electric Power Company (electricity connection); and the Ethiopian Roads Authority (new access roads); Dashen (house construction for the resettled community); and BCM (bulk earthworks and mining).
Contact Details for Project Information
KEFI Gold and Copper, tel +357 2225 6161 or email email info@kefi-minerals.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation
















