Sigma Lithium resumes operations in Brazil after court ruling

Sigma Green Tech plant in Brazil

Sigma Green Tech plant in Brazil

7th October 2026

By: Reuters

  

Font size: - +

Lithium miner Sigma Lithium said on Tuesday it would resume mining and processing at its Grota do Cirilo project in Brazil after a federal appeals court upheld its environmental licences, reinforcing its target of reaching an annualized lithium oxide concentrate production rate of 330 000 tonnes by the end of 2027.

The company said the appeals court overturned an emergency order issued last month by a federal judge in Teofilo Otoni that had suspended its licences, allowing Sigma to fully resume mining and processing operations.

The legal dispute is linked to a lawsuit brought by Ngolo, an association representing local Quilombola communities. Sigma said its operations are outside a newly claimed community perimeter and that its licences were issued in accordance with applicable regulations.

Sigma said it does not need additional mining or processing capacity to meet its 2027 production target, citing available capacity at its South Pit, its existing processing plant and recycling and reprocessing circuits installed following a 2024 upgrade.

The company said its plant had previously produced more than 950 tonnes of lithium concentrate per day, exceeding 1 000 tonnes on several days after the upgrade.

Sigma, which produces lithium concentrate used in battery materials, said it plans to restart a second expansion phase in 2027 that could lift annual capacity to about 580 000 tonnes, followed by a third phase targeting 830 000 tonnes.

Edited by Reuters

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (02/10/2026)
2nd October 2026 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

➕

➕

➕

➕

➕

RESEARCH CHANNEL AFRICA

SUBSCRIBE

➕

➕

➕

➕

➕

➕

➕

➕

➕

➕

CORPORATE PACKAGES

CLICK FOR A QUOTATION

➕

➕







sq:0.039 0.062s - 116pq - 2rq
Subscribe Now