Power of reform

9th June 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

For several years, certain forward-looking commentators argued that by making only a minor amendment to Schedule 2 of the Electricity Regulation Act South Africa could unleash much-needed investment into distributed power generation.

After much resistance and some high-profile “arm twisting”, the amendment was eventually made in August 2021.

As a result, the licensing threshold for distributed generation projects, including those that would wheel electricity using Eskom or municipal grids, was increased from 1 MW to 100 MW, and such projects could be registered with the regulator rather than undergoing onerous licensing.

While registration was initially cumbersome, the system was streamlined and registrations began flowing as intended under the reform, which had been elevated to an Operation Vulindlela priority.

As the electricity crisis intensified and it became clear that the reform represented one of the quickest and cheapest options for introducing new capacity, the 100 MW cap was subsequently removed altogether in December 2022, in line with the Energy Action Plan unveiled by President Cyril Ramaphosa in July of the same year.

The value of the reform is now showing up in statistics, some of which are contained in the most recent Operation Vulindlela progress report, which indicates that the surge in private electricity generation investment continues to “outstrip expectations”.

The report shows that, between January and March this year, the number of distributed generation projects above 10 MW registered with the regulator involved potential projects, primarily solar and wind, with a combined capacity of 2 427 MW.

This represents a massive jump from the 1 664 MW worth of registrations for 2022 as a whole, which had itself been a substantial rise from the 134 MW registered during 2021.

Also highlighted is the strong rise in requests for grid- connection budget quotes from Eskom’s Grid Access Unit. In total, the unit has received budget quote requests for projects with a combined capacity of nearly 13 400 MW, and has issued such quotes for projects with a combined 4 321 MW.

The pipeline of projects “in active development” being tracked by Operation Vulindlela’s Embedded Generation Task Team has grown to 108, and these projects have a combined capacity of just over 10 000 MW. Should they proceed, the projects will involve capital investments of more than R200-billion.

The report also offers some insight into when these projects will begin helping to relieve the country’s debilitating power constraint, showing that more than 1 300 MW should enter commercial operation this year, followed by another 3 000 MW in 2024.

Given that South Africa now needs to build about 8 000 MW of new, mostly variable renewables, capacity yearly to help address the supply gap that has emerged as a result of a failing coal fleet that is also approaching decommissioning, momentum behind this reform needs to be sustained.

Doing so will require progress on the next far bigger set of reforms, many of which are outlined in the Electricity Regulation Amendment Bill currently before Parliament.

Edited by Terence Creamer
Creamer Media Editor

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/03/2024)
15th March 2024 By: Martin Creamer
Gold, hydrogen, mining boost make headlines
Gold, hydrogen, mining boost make headlines
15th March 2024
Magazine round up | 15 March 2024
Magazine round up | 15 March 2024
15th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.109 0.144s - 90pq - 2rq
Subscribe Now