Galantas commissions M3 to update PEA on Andacollo as restart works progress
TSX-V and Aim-listed Galantas Gold Corporation has selected M3 Engineering & Technology corporation to lead an updated preliminary economic assessment on the past-producing Andacollo gold project, in Chile, which is expected to be published in the fourth quarter.
M3 will also lead a crushing plant relocation programme from a site in Mexico to the Andacollo site in Chile.
Galantas CEO Mario Stifano confirms that Andacollo is a permitted brownfield restart project with low capital intensity, supported by an established mineral resource estimate.
Moreover, Galantas tasked NCL Ingeniería y Construcción of Chile to advance the mine design and production schedules, while a company called Stracon is providing mining cost, fleet and execution-planning input.
In parallel, Stifano says the company's project and operations team is advancing infrastructure refurbishment, procurement, contractor engagement and operational readiness at site.
The company targets a potential restart of Andacollo in the first quarter of 2027.
Fortunately, the site has existing infrastructure such as open pits, crushing areas, heap leach facilities, solution ponds, workshops, offices, site roads and an adsorption, desorption and recovery plant.
The existing site infrastructure, coupled with the moved crushing plant, is expected to lower the capital intensity to restart the Andacollo operations, shorten the restart schedule and reduce execution risk for the company.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation