Cost-saving plant proving its worth

The parking lot roof top solar plant at Volkswagen Group Africa's component plant in Kariega, in the Eastern Cape

SOLAR PARKING The parking lot roof top solar plant at Volkswagen Group Africa's component plant in Kariega, in the Eastern Cape, is already making a dent in the company's electricity costs

4th September 2026

By: Halima Frost

Senior Staff Writer

     

Font size: - +

Since its commissioning in June, the PV solar project at vehicle manufacturer and exporter Volkswagen Group Africa’s (VWGA’s) component plant in Kariega, in the Eastern Cape, has successfully generated more than 180.21 MWh, saving the facility about R541 000 in electricity costs to date, while avoiding about 169 t of CO2-equivalent emissions says VWGA sustainability lead Ntsapokazi Ningiza.

This project reinforces VWGA’s commitment to sustainability and renewable energy.

“As part of our broader decarbonisation strategy, we have plans to expand on embedded solar generation through additional solar PV installations where it is feasible to do so, both from a space and a finance perspective,” she adds, noting that these potential installations will not be limited to the Kariega facilities.

The PV project, completed in June 2026, comprises 1 410 solar panels mounted on the roofs of the building and its car park, as well as a ground-mounted portion.

“This facility has a capacity of about 0.88 MWp and is the latest addition to VWGA’s renewable-energy projects,” says Ningiza.

The project was not the first green energy installation, as 40% of Kariega’s energy requirements had already been fulfilled using green sources in 2025.

VWGA previously completed a multi-phase solar panel installation over its employee car park, which included 9 294 panels with a capacity of 5.2 MWp and is capable of producing 7 125 MWh/y.

Additionally, similar solar panel projects were completed on the roof of the VWGA final assembly building with a generating capacity of 1.7 MWp, as well as on top of the engine plant generating 1.0 MWp. Other smaller installations include 0.2 MWp at Product Development and 0.4 MWp at Group Parts warehouse in Centurion, Gauteng.

“We have made significant strides in recent years towards fully sustainable manufacturing,” relays Ningiza.

To monitor and maintain the solar installations, software is used in-house to track performance in real time, while a dedicated service provider conducts scheduled maintenance to ensure maximum yield.

These projects form part of a long-term sustainability roadmap towards achieving carbon-neutral electricity in VWGA’s production operations.



Edited by Nadine James
Features Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mount Lyell copper/gold/silver project in Tasmania.
Two new projects win Sibanye-Stillwater thumbs up
2nd September 2026 By: Martin Creamer
Resources Watch
Resources Watch
2nd September 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.067 0.091s - 118pq - 2rq
Subscribe Now