TSX-listed Cameco has temporarily suspended production at its Cigar Lake uranium mine, in Saskatchewan, owing to challenges at the Orano McClean Lake mill where Cigar Lake's ore is processed.

Orano has encountered operational issues with the sulphuric acid plant at McClean Lake, which caused it to shut down for repairs.

While Orano awaits replacement parts to complete the repairs and bring the acid plant back online, it is assessing options to obtain acid supply from an alternative source.

With limited ore storage capacity at Cigar Lake, Cameco opted to temporarily suspend mining activities until sufficient acid is available to allow milling to resume at McClean Lake.

"At present, we expect the McClean Lake mill to return to operation in about two weeks, and we do not expect the disruption to impact our 2026 production outlook for Cigar Lake. However, there is a risk that the repairs to the acid plant take longer than planned and that mining at Cigar Lake is unable to resume on the expected schedule.

"Depending on the duration of any additional delays, our 2026 production outlook could be impacted," Cameco states.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 
Rosond
Rosond

ROSOND provides fast, efficient, safe, and cost-effective drilling and grouting services to mining and exploration industries throughout Africa.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.027 0.05s - 115pq - 2rq
Subscribe Now