Bushveld reports stable production, but lower sales

31st July 2024

By: Creamer Media Reporter

     

Font size: - +

Integrated primary vanadium producer Bushveld Minerals produced 838 t of vanadium for the quarter ended June 30, taking production for the first half of this year to 1 693 t.

Production was lower than the 840 t and 1 784 t produced in the second quarter and first half of 2023, respectively.

"I'm pleased that we could continue to rationalise assets in this period, as well as progress on the turnaround work at Vametco, now our core asset. Despite a slight drop in production due to equipment failure owing to cash constraints at Vametco earlier in the year and a planned shutdown at Vanchem, we maintained steady overall production levels.

"I'm delighted to report that the team at Vametco is pushing through a turnaround plan, and in May achieved 217 t, the highest monthly production since I joined a year ago.

"These initial efforts, and a number of other initiatives identified at Vametco, will be executed in the second half of this financial year, putting us on track to achieve our overall target of 240 t monthly sustainable production at Vametco by the fourth quarter," comments Bushveld CEO Craig Coltman.

Sales were, however, significantly lower year-on-year. Bushveld sold 759 t of vanadium in the second quarter, compared with the 1 068 t sold in the second quarter of 2023, while sales of 1 639 t for the six months to June 30 was lower than the 2 096 t sold in the first half of 2023.

The sale of Bushveld's Vanchem operation is under way and awaiting Competition Commission approval, which is expected by the end of October.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

The Zinkgruvan mine in Sweden
Lundin sells two European mines to Boliden
Updated 2 hours 52 minutes ago By: Mariaan Webb

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 06 December 2024
Magazine round up | 06 December 2024
6th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.092 0.125s - 144pq - 2rq
Subscribe Now