Bunker Hill Mining expects first concentrate batch by month-end
TSX-listed Bunker Hill Mining Corporation says commissioning of its new 1 800 t/d processing facility in Kellogg, Idaho, is on track to produce its first batch of concentrate for sale by the end of June.
The company is focused on restarting the historic Bunker Hill mine, in Idaho's prolific Silver Valley, with the project focused on silver, zinc and lead production.
"Our crusher is now processing ore and feeding the ore silo as we complete final commissioning of the grinding, flotation, thickening and filtration circuits. These activities are being carried out in parallel with the commissioning of our co-located tailings filter press within a fully operational closed-loop water management system," confirms Bunker Hill Mining CEO and president Sam Ash.
Having successfully commissioned the plant using waste rock, the company is now transitioning to run-of-mine ore from the silo, with concentrate production expected to follow shortly.
"While commodity markets and investors continue to navigate an evolving global economic and geopolitical landscape, our team in Idaho's Silver Valley remains focused on what we can control: executing safely, methodically and with precision.
"Every day, this dedicated group of professionals is taking another step toward bringing America's newest mine into production on schedule," Ash concludes.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation