Project development at Kefi’s Ethiopia project advancing on schedule
Aim-listed Kefi Gold and Copper has reported that the Phase 1 resettlement action plan (RAP) at its Tulu Kapi gold project, in Ethiopia, clearing the mining licence area for the installation of initial infrastructure, is well advanced, with 100% of compensation agreements now completed.
Preparations for the Phase 2 RAP, covering the openpit mining and plant areas, are now under way.
Kefi notes that project equipment procurement continues as planned, with more than 50% of major equipment already ordered or ready for ordering.
Principal contractors Lycopodium, Ethiopian Electric Power (EEP), Ethiopian Roads Administration (ERA) and BCM are now intensively mobilising personnel, subcontractors and systems on the ground. Physical construction, to date, comprises house-building for resettlement, installation of an electrical substation and the new access road.
Kefi executive chairperson Harry Anagnostaras-Adams says that, following the successful assembly of the Tulu Kapi financing arrangements for the openpit and process plant, the company’s focus is firmly on project execution and on closing the debt drawdown processes.
He adds that progress across community resettlement, plant procurement and construction subcontractor tendering is in line with schedule.
“We have developed strong working relationships with government, local communities and our international financing and contracting partners,” he says.
“While global markets have been volatile for our sector, in particular since the start of the Iran War, our implementation programme remains on track. We are well-positioned and we continue to work closely with all stakeholders to deliver Ethiopia's first modern, internationally financed gold mine,” he adds.
Anagnostaras-Adams says the company is also advancing development plans for self-funded production growth at Tulu Kapi and in the minority-owned portfolio in Saudi Arabia, and to establish a platform for a portfolio of projects across Ethiopia and the region.
The company says all key project milestones at Tulu Kapi are tracking on schedule, with commissioning targeted to begin in late 2027 for full production in mid-2028 from the openpit and process plant.
The company explains that development planning teams in Ethiopia and Saudi Arabia are focused on production growth in both countries which is intended to be self-funding and a re-assembled exploration team has started to evaluate and prioritise opportunities across now-familiar and highly prospective geological terranes in Ethiopia and the wider region.
Kefi has recently re-assembled a highly successful exploration team under exploration head Jeff Rayner, who has deep experience in Ethiopia.
The company says the team is now evaluating and prioritising opportunities both close to Tulu Kapi and in other under-explored but highly prospective areas. New opportunities will be judiciously advanced while Kefi prioritises construction at Tulu Kapi.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation