Lafigué gold project, Côte d’Ivoire – update

Image of gold nuggets

12th May 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Lafigué gold project.

Location
On the Fetekro property, in Côte d’Ivoire.

Project Owner/s
Endeavour Mining.

Project Description
Lafigué has proven and probable reserves of 49.8-million tonnes grading 1.69 g/t gold.

The deposit is amenable to conventional openpit, drill-and-blast mining, which will be undertaken by contractors.

The openpit will be developed in six stages, with a maximum mining capacity of 55-million tonnes a year.

The mine will produce an average of 203 000 oz/y at an over a 12.8-year mine life.

Ore mining will occur in three to four flitches, selectively using smaller loading equipment to decrease dilution.

Diesel excavators and trucks will be used for loading and haulage, with a fleet comprising 400 t class face shovels to load 180-t-capacity dump trucks for waste mining, and 200 t class excavators to load 180-t-capacity dump trucks for ore mining.

Ore will be processed through a four-million-tonne-a-year processing plant, based on only a fresh ore feed. The operation will involve two-stage crushing, followed by a high-pressure grinding roll and ball milling circuit.

New infrastructure will be added to support mining, processing and waste management on the mining licence, including 6.6 km of internal roads, a 32 km power transmission line, emergency diesel generators, and additional site facilities and accommodation for staff. In addition, space has been allocated to the north of the existing processing plant to potentially incorporate a solar power facility in the future.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of $664-million and an internal rate of return 25% at a $1 500/oz gold price, with a payback of 3.9 years.

Capital Expenditure
The project has an upfront capital cost of $448-million.

Planned Start/End Date
First production is expected early in the third quarter of 2024.

Latest Developments
Endeavour has reported that its Lafigué greenfield build is progressing well, with the project being on time and within budget.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Endeavour Mining, tel +44 203 011 2723 or email info@endeavourmining.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 
Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.046 1.094s - 111pq - 2rq
Subscribe Now