Kore Potash progresses DFS for RoC project

SEAN BENNETT Kore used the quarter ended March 31 to start the process of optimising the capital and operating expenditure estimates, execution schedule and the final designs

SEAN BENNETT Kore used the quarter ended March 31 to start the process of optimising the capital and operating expenditure estimates, execution schedule and the final designs

Photo by Dylan Slater

30th April 2018

By: Nadine James

Features Managing Editor

     

Font size: - +

JOHANNESBURG (miningweekly.com) – Potash exploration and development company Kore Potash, headed by CEO Sean Bennett, continues to make progress with the definitive feasibility study (DFS) for its flagship 97%-owned Sintoukola (Kola) Potash project, in the Republic of Congo (RoC).

The DFS, which is being undertaken by a French consortium, has moved from design engineering to estimating final construction costs and the execution schedule.

Kore used the quarter ended March 31 to start the process of optimising the capital and operating expenditure estimates, execution schedule and the final designs.

The DFS schedule was slightly revised, owing to additional redesign work related to further optimisation of the flotation area of the process plant.

Third-party testing of the optimised designs have been completed with results supporting an improved recovery from the prefeasibility study.

Further, the final test results for the optimised float circuit have been received and they have shown positive results that support the inclusion of the optimisations in the DFS. The company expects to publish the final results of the DFS by the third quarter.

Meanwhile, the procurement process is nearing completion, with most packages finalised for the DFS. The issuance of the final material off-take agreements has begun.

Final report writing is under way, with draft documents expected in the second quarter.

The shaft design has also been finalised. The Kola deposit will be accessed by two 7-m-diameter shafts with depths of about 260 m. The intake shaft will include a man and material cage, while the exhaust shaft will be equipped with a pocket belt ore hoisting system.

The hydrogeological testing and modelling are complete, so too are the detailed engineering designs of underground facilities.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

North Ridge Pumps
North Ridge Pumps

North Ridge Pumps is an independent manufacturer of pumps. We have a proven track record for product support and customer service throughout the...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.048 0.603s - 128pq - 2rq
Subscribe Now