King of the Hills' ramp-up slower than hoped

27th October 2022

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – The ramp-up of gold production from the King of the Hills operation, in Western Australia, progressed slower than anticipated in the three months to September, gold miner Red 5 said on Thursday.

The project produced 26 710 oz of gold during the quarter, up from the 18 586 oz produced in the June quarter, with gold sales increasing from 16 587 oz to 30 005 oz in the same period.

However, Red 5 noted that the ramp-up schedule for the September quarter had been impacted by Covid-absenteeism, delaying progress towards higher-grade openpit benches and underground production stopes.

Additional crews have been in place since August to enable the mining schedule to catch up by December 2022.

Furthermore, unplanned downtime was experienced in the processing plant, with mill shutdowns required in September to reconfigure the semi-autogenous grinding (SAG) mill to process an increasingly hard primary rock charge as ore feed.

“Following the first gold pour on June 5 and the successful delivery of the A$226-million King of the Hills project, the main focus during the September quarter was to progress the ramp-up of all aspects of the new operation. The King of the Hills and Darlot mining operations delivered production of 26 710 oz in the September quarter and gold sales of 30 005 oz,” said MD Mark Williams.

“As outlined recently, the ramp-up of mining at King of the Hills has been impacted by Covid absenteeism and unplanned downtime in the processing plant, which reduced availability and mill throughput rates.

“In September, the SAG mill has also been adjusting to a harder rock blend as the production of hard rock ore from the mines ramps up, transitioning from the oxide material in the stockpiles and openpit. Since the end of the quarter, the ramp-up of throughput at the SAG mill and within the processing circuit has performed more in line with expected production rates.

“We have implemented measures to address the issues experienced in the September quarter and, importantly, the King of the Hills mill overall is performing largely in line with expectations, achieving sustained periods at design throughput rates during the reporting period and into October,” said Williams.

At the start of October, Red 5 completed a capital raising to assist with working capital and to fund the next phase of its growth programme, including a planned expansion of the King of the Hills processing plant to increase throughput capacity from the current 4.7-million-tonne-a-year nameplate to a targeted 5.5-million tonnes a year.

“During the quarter we also delivered an updated resource and reserve statement which reinforced the exceptional endowment of King of the Hills orebody, with a 7% increase in the King of the Hills mineral resource to 4.7-million ounces of contained gold and a 12.5% increase in the ore reserve to 2.7-million ounces.

“Our global mineral resource base across the Eastern Goldfields, including the King of the Hills and Darlot mining operations and our satellite deposits, increased by 10% to total 6.6-million ounces of contained gold.”

Edited by Creamer Media Reporter

Comments

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.199 0.237s - 108pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: