Expandable graphite plant, India

Image of graphite

Photo by © Bloomberg

14th October 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Expandable graphite plant.

Location
Special economic zone in Pune, India.

Project Owner/s
Panthera Graphite Technologies, a 50:50 joint venture between Blackearth Minerals and Metachem Manufacturing.

Project Description
Expandable graphite, along with lithium-ion bat­teries, is one of the fastest growing markets.

The plan is to develop a plant that can produce 2 000 t/y to 2 500 t/y of expandable graphite in the initial stages, and then to expand production to between 4 000 t/y to 5 000 t/y from Year 4.

The development of expandable graphite involves treating flake graphite and heating it to cause the flakes to split apart, expand and increase hundreds of times in volume. This material is compressed into sheets to create a foil that can be cut into shapes and be used in many applications, including consumer electronics, high-end gaskets that are heat and corrosion resistant, fire retardants, smart building products, flow batteries and fuel cells.

Graphite concentrate will be sourced from external parties for years 1 to 2 of operations.

The project has a 25-year mine life.

Potential Job Creation
The project will largely employ local labour.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value of $78-million and an internal rate of return of 571%, with a payback of 1.2 years.

Capital Expenditure
The first stage of the project is expected to entail an investment of $3-million.

Planned Start/End Date
Site development is expected to start in September, with planned completion in early 2023, and trial processing to be undertaken immediately thereafter. The plan is to start the supply of expandable graphite in the second quarter of 2023.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Blackearth Minerals, tel +61 8 6145 0289 or email info@blackearthminerals.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Projects

Copperwood project, US
Updated 4 hours ago By: Sheila Barradas

Latest News

Glencore studying an approach for Anglo American, sources say
Glencore studying an approach for Anglo American, sources say
Updated 34 minutes ago By: Reuters

Showroom

Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.115 0.174s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: