Eldorado enters final commissioning stages of Skouries processing plant
TSX- and NYSE-listed Eldorado Gold Corporation has crushed first ore at the Skouries copper/gold project in Greece, with the site now being in the final stages of construction.
Having entered the commissioning phase in July, Eldorado says the first ore is now being processed through the crushing circuit, with first production of copper/gold concentrate targeted before the end of the third quarter.
Commercial production from the Skouries plant is expected during the fourth quarter, subject to Eldorado completing final site energisation and ramp-up activities. In this regard, Eldorado says the final transmission tower has been installed, with full site energisation remaining contingent on final inspection and sign-off by the relevant Greek authority. The company has added additional generators to provide interim power for the processing plant as required.
CEO George Burns comments that the first ore having been fed through the commissioned crushing circuit is an important demonstration that the front-end processing of the plant is operating as expected. He adds that wet and dry commissioning activities are progressing across the crushing, grinding, flotation, concentrate handling and tailings circuits.
Openpit mining at Skouries, meanwhile, continues to run ahead of schedule. The company has an ore stockpile of about 3.9-million tonnes, which will provide ore feed through 2026 and support the first full year of production.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation