Zandkopsdrift rare-earth element project, South Africa

4th April 2014

  

Font size: - +

Name and Location
Zandkopsdrift rare-earth element project, Northern Cape, South Africa.

Client
Frontier Rare Earths and Korea Resources Corporation (Kores).

Project Description
Zandkopsdrift has one of the biggest total rare-earth oxide (REO) grades and the highest-grade REOs of significantly advanced rare earths deposits outside China.

Envisioned is a standalone opencast mine, which will be mined by conventional free-dig and/or drill, blast and haul techniques, with minimal drilling and blasting required. The steady-state mining production target is one-million tons a year and the total separated rare-earth oxides target production rate is 20 000 t/y.

Infrastructure associated with the mine and process plant includes the upgrade of existing district roads from the surrounding towns to the mine.

The water supply to the mine will be provided by Frontier from demineralised water, piped 35 km from a desalination plant.

Turbogenerators will supply power using the on-site exothermic reactions within an on-site sulphuric acid production plant.

The desalination plant will be powered by diesel generators and the Saldanha separation plant will be supplied by State-owned power utility Eskom.

Value
$910-million, which includes capital expenditure requirements for the Zandkopsdrift mine, related infrastructure and services, land purchases, mine closure and rehabilitation provision, the upgrading of local district roads, the provision of the social and labour plan, as well as the Saldanha separation plant, with its related infrastructure and services.

Duration
Along with its strategic partner, Kores, Frontier intends to start rare earths production in 2016, with a target production capacity of 20 000 t/y of separated REOs.

Latest Developments
Frontier Rare Earths expects to release the results of its prefeasibility study (PFS) this year, after determining that it requires more testwork to improve the flow sheet.

Capital and operating costs of the mine, processing plant and related infrastructure are expected to be higher than the initial economic assessment in 2012, but will be partially offset by lower capital and operating costs for the rare earths separation plant.

The completed PFS was presented to the company for review during the third quarter of 2013. It identified several areas where engineering-design and process improvements could be made that were expected to have a “potentially significant” positive impact on the estimated capital and operating costs of the Zandkopsdrift processing plant and the Saldanha separation plant.

Value engineering and process optimisation studies are currently under way. Other areas of improvement are also being investigated.

The company has also said that while it is initially planned that any process improvements recommended by the feasibility study testwork will be introduced during the feasibility study, it has decided that the positive impact is potentially big enough that it should be included in the PFS.

The proposed process improvements include a flow sheet that is expected to result in a higher proportion of higher-value critical rare earths and higher-purity products being produced through another rare-earth element recovery method and a new processing technology.

This will, in turn, lead to a basket price for Zandkopsdrift production at current free-on-board China prices of $44/kg, compared with an in-situ basket price of $36/kg.

Key Contracts and Suppliers
Venmyn SNC-Lavalin (preliminary economic assessment); Mintek and SGS Mineral Services (metallurgical flow sheet development); the MSA group (resource estimation); Sound Mining Solutions (mine design and schedule); Epoch Resources (design of tailings disposal facility); SNC Lavalin (separation plant engineering design and capital operating cost estimates) and DRA (engineering design and operating cost estimates for Zandkopsdrift).

On Budget and on Time?
Project is on schedule

Contact Details for Project Information
Frontier Rare Earths (Luxembourg), tel +352 208 80249 or email ir@frontierrareearths.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

ZF Aftermarket
ZF Aftermarket

ZF Aftermarket is the after-sales division of the world-renowned German ZF group, a global leader in mobility technology.

VISIT SHOWROOM 
Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.046 0.795s - 111pq - 2rq
Subscribe Now