Wiluna Stage 1 sulphide project, Australia – update

25th June 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Wiluna Stage 1 sulphide project.

Location
The Yilgarn Crayton, in the Northern goldfields of Western Australia.

Project Owner/s
ASX-listed Wiluna Mining.

Project Description
The project involves the staged development of the sulphide operation from its current production of an estimated 62 000 oz/y from mining free milling ore through the current 2.1-million-tonne-a-year carbon-in-leach (CIL) processing facility, to initially produce between 100 000 oz/y and 120 000 oz/y of gold and gold in concentrate.

This transition will be realised using the current, recently refurbished crushing circuit, as well as the previously expanded mill circuit and a new 750 000 t/y concentrator.

Wiluna is further planning to increase production by at least doubling the mining rate, and increasing production by the concentrator to an estimated 250 000 oz/y of gold by the end of 2023 or early 2024.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The estimated cost of the project is A$81-million.

Planned Start/End Date
Wiluna Mining Corporation is targeting a full ramp-up of production of 120 000 oz/y at its Wiluna operation by the end of 2022.

Latest Developments
The Stage 1 750 000 t/y flotation plant is about 54% complete and mine development about 35% complete.

Underground operations are ramping up, with Wiluna’s focus remaining on securing short-term production and cash flow from the Golden Age orebody, and to continue the progressive rehabilitation of existing access and infrastructure to establish the initial stoping production areas for the start of concentrate production for Stage 1 of the operation.

The company has noted that the feasibly study for the Stage 2 operation, which would increase flotation plant capacity to 1.5-million tonnes a year, is progressing well.

The feasibility study is planned for completion at the end of 2021.

Key Contracts, Suppliers and Consultants
GRES (engineering, procurement and construction contractor for the Stage 1 works) and Byrnecut Australia (underground development and production mining services).

Contact Details for Project Information
Wiluna Mining, tel +61 8 9322 6418 or email info@wilunamining.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

CSIR International Convention Centre (CSIR ICC)
CSIR International Convention Centre (CSIR ICC)

CSIR International Convention Centre (CSIR ICC) - the leading conference and events venue in Pretoria/Tshwane.

VISIT SHOWROOM 
Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.041 0.853s - 111pq - 2rq
Subscribe Now