Wesizwe swings to R41m loss as delays to Bakubung start-up continue

11th March 2022

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

JSE-listed Wesizwe Platinum has posted a basic loss a share of 1.51c for the year ended December 31, 2021, compared with earnings a share of 3.18c reported for the prior year.

The loss before tax for the year was R41.2-million, against a profit of R52.8-million in 2020. ­­

Wesizwe says the company will not earn revenue from mining activities until construction of the Bakubung platinum mine is completed. The mine was temporarily closed as of February 8 following a strike by its surrounding Ledig community, which started on January 26.

The company in 2020 also halted construction activities at the mine, owing to delays in public consultations required for the company’s water-use-licence application and environmental-impact assessment, as a result of Covid-19.

The loss for the year takes into account administration expenses of R37.4-million, finance income amounting to R48.4-million and finance expenses amounting to R53.1-million.

Wesizwe’s cash resources stood at R374-million at the end of 2021. Its liabilities, which include shareholders’ loans of R1.4-billion, exceed the current assets by R784-million.

The ability of the company to continue as a going concern is dependent on the support of the majority shareholder and the majority shareholder not calling on the current shareholder’s loans, it says.

Wesizwe reports that its main shareholder, in a letter of comfort, stated its commitment to the company despite shortfalls.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
CSIR International Convention Centre (CSIR ICC)
CSIR International Convention Centre (CSIR ICC)

CSIR International Convention Centre (CSIR ICC) - the leading conference and events venue in Pretoria/Tshwane.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 1.141s - 110pq - 2rq
Subscribe Now