Weatherly’s Tschudi mine delivers copper cathode production above nameplate production rate
JOHANNESBURG (miningweekly.com) – Aim-listed Weatherly International’s Tschudi mine, in Namibia, produced 4 442 t of copper cathode in the quarter ended March 31 – 4% above the mine’s nameplate production rate of 17 000 t/y.
The openpit copper mine had achieved nameplate production of 17 000 t/y in December and was considering options to increase processing capacity to 20 000 t/y.
"We are very pleased with the consistent production performance from Tschudi during the quarter . . . continuing our record of meeting or beating guidance at Tschudi,” Weatherly CEO Craig Thomas said on Thursday.
He added that the Namibian dollar/US dollar exchange rate movements had assisted the company in keeping its US dollar production costs well below forecast.
However, Thomas believed a focus on productivity and cost discipline by the team on site had also contributed to the “satisfying results” for the quarter.
C1 costs for Tschudi for the quarter were $3 429/t, remaining “well below” guidance of the $4 250/t to $4 350/t for the current financial year.
In December, the company announced an amended agreement with Orion Mine Finance for the Tschudi debt facilities, including certain hedging arrangements to be agreed between Orion and Weatherly during the third quarter of the 2016 financial year.
The result of these arrangements to date was that the average price received during the March quarter was $4 742/t. Planned production of about 4 250 t for the June quarter had been pre-sold to Orion at $4 912/t.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation