Vulcan Energy delays lithium output target by a year
FRANKFURT - Lithium supplier Vulcan Energy is around a year behind schedule to reach an annual capacity of 40 000 t because of supply chain delays, the company's chief executive told Reuters on Monday.
Plans to build a sample facility in the summer of 2022 were held back by material shortages because of supply chain bottlenecks, delaying the feasibility study the company hopes to use to attract the more than €1.7-billion it requires in investment.
The study will now come out in early 2023, with 40 000 t of output reached by the end of 2026 rather than 2025 as first announced, CEO Horst Kreuter said.
Vulcan Energy already has offtake agreements with automakers Volkswagen, Stellantis and Renault, as well as Umicore, LG Chem's battery unit LG Energy, and utility firm MVV Energy.
Agreements range from five and six year terms to 20 years for the utility firm.
It now expects to extract 18 400 t of lithium in its first year of operation in 2025, using a new technology which extracts lithium-rich brine from water in underground reservoirs.
Yet onlookers like Germany's Karlsruhe Technology Institute (KIT) see even the postponed plan as unrealistic, pointing out that the technology is untested and still needs to obtain various licences.
A study conducted by the Institute earlier this year said that it would take 20 extraction sites to reach a volume of about 40,000 tonnes of lithium per year, which could not be set up before the end of the decade.
Asked about the study, Vulcan Energy - which has licences for about 1 500 km2 of land in Germany - argued its technology was so efficient it could extract the 40 000 t from just five sites.
"We base our forecasts on the status of the technology, not the theory," Kreuter said. "We know how it works."
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation