Valence near to financing deal
PERTH (miningweekly.com) – Graphite miner Valence Industries on Tuesday told shareholders that the company was concluding negotiations to secure A$50-million in financing for the proposed expansion of its Uley graphite project, in South Australia, as the mine readied for its first shipment of ore.
A previously completed feasibility study estimated that the Phase 2 expansion of the Uley project would require a capital investment of about A$37-million, over a three-year period, to increase production from the current Phase 1 level of 14 000 t/y to 50 000 t/y.
The expansion of the Uley site would provide additional processing capacity in 25 000 t/y increments of graphite output, to reach 64 000 t/y, to effectively match market demand.
MD and CEO Christopher Darby said on Tuesday that the production ramp-up commissioning at the Uley project was progressing as planned, with export shipments expected to increase to the targeted rate of 14 000 t/y by the third quarter of this year.
The first stage of the expansion programme, which would more than double the production capacity to 39 000 t/y, was expected to be completed during 2016, along with the delivery of advanced materials handling and processing capacity in Adelaide.
Meanwhile, Valence also noted that the first shipment of Uley graphite was scheduled to leave Port Adelaide on Tuesday.
Some 20 t of flake graphite were trucked from Port Lincoln to Valence Industries’ Port Adelaide logistics handling facility in March this year, in preparation for export to customers in Asia Pacific.
The graphite was now being shipped to customers.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation