Updated Valentine feasibility study presents 3-pit mine plan

8th December 2022

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Toronto-listed Marathon Gold has presented an updated feasibility study for the Valentine gold project, in Newfoundland and Labrador, outlining plans for a three-pit mine plan with increased mineral reserves, an extended mine life and a higher production profile.

The study incorporates the same conventional openpit mining and milling strategy employed in the April 2021 feasibility study, but is based on three pits: the Marathon, Leprechaun and Berry deposits.

Marathon already has federal and provincial approval to mine at the Leprechaun and Marathon deposits – with early construction work having already started – and it will now work towards including the Berry deposits.

The addition of the Berry deposit will “significantly improve” the project’s production profile, president and CEO Matt Manson said in a statement.

In terms of direct, high-grade ‘mill feed’ (ore with a cut-off grade of 0.7 g/t gold), Marathon is now forecasting 195 000 oz/y over 12 years, compared with 179 000 oz/y over nine years previously.  All-in sustaining cost (AISC) will average at $1 007/oz.

In the first three years, production will average 200 000 oz/y at an AISC of $890/oz.

“This is expected to generate substantial cash flow in the early years of mining,” said Manson.

“Our approach to mining Valentine is to present a large project with a high strip, supported by a high-grade mineral resource that we have focused on derisking, openpits optimised on cautious gold price cases of between $950/oz and $1350/oz, and a real-market operating cost build-up,” he said.

Other aspects of the mine design, such as the site layout, basic mill flow-sheet, mill expansion strategy, thickened tailings deposition strategy, 400-person camp, and low-cost site power via the NL Hydro power grid, remain as previously conceived.

The cost-to-complete estimate for Valentine is C$463-million, which is slightly below the C$470-million to C$490-million estimate guided in September.

“Since early works at the project have already commenced, our updated capital and operating cost estimates benefit from a level of procurement, labour force development and engineering design that is at a higher level than typical for a feasibility-level study,” noted Manson.

Marathon has more than 24 months during construction to bring Berry into the permitted mine plan in time for it to contribute to the first year of operations. The regulatory process that assesses the deposit will be primarily at the provincial level.

“The Valentine gold project is well on its way to being the largest gold mine in Atlantic Canada. It will be the most important new mining project in Newfoundland and Labrador since Voisey’s Bay, and a major contributor to the socio-economic wellbeing of Newfoundland’s central region.”

Edited by Creamer Media Reporter

Comments

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
SBS Tanks
SBS Tanks

SBS® Tanks is a leading provider of innovative water security solutions with offices in Southern Africa, East and West Africa, the USA and an...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.302 0.338s - 109pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: