https://www.miningweekly.com
Contractor|Copper|Exploration|Gold|Hydropower|Mining|Power|PROJECT|SECURITY|Underground|Equipment
Contractor|Copper|Exploration|Gold|Hydropower|Mining|Power|PROJECT|SECURITY|Underground|Equipment
contractor|copper|exploration|gold|hydropower|mining|power|project|security|underground|equipment

Tulu Kapi gold project, Ethiopia – update

Image of gold nuggets

19th November 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Tulu Kapi gold project.

Location
Western Ethiopia.

Project Owner/s
Kefi Gold and Copper (formerly KEFI Minerals) will own 80% of the exploration and holding company for Ethiopia, KME, which, in turn, will own 56% of Tulu Kapi Gold Mines Share Company (TKGM), thus bestowing Kefi with a 45% beneficial interest in the project.

Project Description
Tulu Kapi has an ore reserve estimate of 15.4-million tonnes at 2.1 g/t gold for 1.1-million ounces of gold.

Openpit gold production is estimated at 140 000 oz/y over a seven-year mine life.

Total life-of-mine production is estimated at 980 000 oz.

The conventional openpit mining operation will include a carbon-in-leach processing plant. The mine will be connected to Ethiopia’s electricity grid through a new 47-km-long, 132 kV dedicated power line relatively close to the country’s major hydropower-generation source. An emergency diesel power plant will also be installed to provide emergency backup power for critical process equipment in the event of a grid power failure.

A preliminary economic assessment has indicated the economic attractiveness of mining the underground deposit adjacent to the Tulu Kapi openpit after the startup of the openpit and the repaying of project debts through positive cash flows.

Potential Job Creation
About 150 local personnel have been employed to prepare new host lands.

TKGM has started compensation procedures for the small portion of the community who is to be resettled and occupies the site for the planned electricity substation. Starter homes have been fabricated and are being delivered to site for assembly.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
While there have been no material changes in the estimated $253-million in capital costs of the project – comprising about $221-million for development, about $21-million for sustaining capital and about $21-million for closure costs – a standby facility has now been included in the finance plan to provide additional headroom.

Planned Start/End Date
Commissioning of the project is planned for 2023, with key development activities due to start in December 2021.

Latest Developments
Kefi Minerals expects to receive project finance confirmation for its Tulu Kapi gold project by the end of January, with the project’s full launch expected between February and May.

The country’s Ministry of Mines also confirmed a licence for the project, valid until 2035, in early November.

These developments follow a temporary pause of the project during September and October, owing to the prohibition of site access imposed by government security authorities, which followed the abduction of four staff members.

Kefi’s beneficial interest in the project is now expected to be about 70%, up from the 45% expected in 2020, making the project “significantly value accretive”.

Key Contracts, Suppliers and Consultants
Corica Group (mining contractor).

Contact Details for Project Information
KEFI Gold and Copper, tel +90 232 381 9431, fax +90 232 381 9071 or email info@kefi-minerals.com.

Edited by Creamer Media Reporter

Comments

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.137 0.194s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: