https://www.miningweekly.com

Tulu Kapi gold project, Ethiopia

1st February 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Tulu Kapi gold project.

Location
Ethiopia.

Client
Kefi Minerals.

The Tulu Kapi Mines Share Company (TKGM) will hold the Tulu Kapi project. 

Project Description
A definitive feasibility study (DFS) update for the project was completed in May 2017.

The 2017 DFS incorporates due diligence and refinements since the 2015 DFS, and provides increased confidence in the company’s plans to develop the project.

The 2017 DFS has similar outcomes to those of the 2015 DFS.

The mining method planned is conventional openpit drill-and-blast, load-and-haul, reflecting a semiselective mining approach, whereby a bulk mining approach is applied to 79% of ore, or 95% of all material, and a selective mining approach to 21% of ore, or 5% of all material.

The processing plant comminution circuit, refined and primary semiautogenous (SAG) mill, and secondary ball mill circuit have been replaced with a larger SAG‐only circuit. The DFS‐approved grind size for the processing plant has increased from P80 = 75 μm to 150 μm.

The designs for the tailings storage facility (TSF) and water storage dams have also been revised. The TSF has been relocated downstream to reduce capital costs, with no reduction in capacity for a neutral balance.

New access roads have also been refined to decrease capital costs.

Key planning assumptions that have been introduced since the 2017 DFS include:

reworked production plans for years 1 to 3, with forecast gold production expected to expand from 115 000 oz/y in the 2017 DFS to 145 000 oz/y;

expanding the capacity of the project’s processing plant to between 1.9-million and 2.1-million tonnes a year, depending on the hardness of the ore; and

recasting the mining plans to allow for faster mining, intensified grade-control drilling and enhanced flexibility to switch between bulk mining and selective mining.

Various components remain unchanged from the 2015 DFS, including geology and mineralisation (ore reserves and mineral resources), metallurgical testwork data, and environmental and social permitting.

Mining the underground deposit below the planned openpit has not yet been fully considered and will be addressed in due course.

A preliminary economic assessment completed in early 2016 evaluating the current indicated resource – 1.1-million tonnes grading 5.6 g/t gold – has indicated that the addition of an underground mine has the potential to increase total openpit and underground gold production to more than 150 000 oz/y over four years.

The orebody remains open and further potential will be added.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The net present value (NPV) of the project at the start of construction on a 100% basis is estimated at $175-million. The internal rate of return has increased from 22% in the 2015 DFS to 60%.

Payback is three years.

Value
The $160-million total funding requirement for the project is consistent with Kefi’s recent guidance for required funding.

The additional $12-million funding required for the reworked production plans, and the plant and infrastructure expansion announced at the end of October 2017, have been offset by other savings and financier Oryx Management’s offering to expand its facility from $135-million to $140-million.

In addition, the reworked estimates also reflect the strategy agreed with Oryx Management to install greater processing capacity from the outset to achieve: 
• a quicker cash flow from the openpit and capacity to process additional ore from targeted satellite deposits, and
• greater protection against downside risks by facilitating the faster processing of lower-grade ore from the openpit.

Duration
Construction of Tulu Kapi is expected to start early in 2019 and commissioning is expected for the second half of 2020.

Latest Developments
Kefi Minerals’ Ethiopian private-sector project partner ANS Mining has increased its investment commitment to subscribe for new shares in TKGM to the Birr equivalent of $38-million, compared with the previously planned commitment of $30-million.

ANS has also nominated its appointees to the TKGM board as per its right under a September 2018 subscription agreement.

Kefi advised earlier this month that a number of formal consents by government for the development of the Tulu Kapi mine remained outstanding.

Those consents have now been received from the relevant agencies.

Accordingly, upon ratification by the Prime Ministry, Kefi will be in a position to start project development.

Kefi has also confirmed that its Ethiopian public-sector project partner, the Federal Ministry of Finance and Economic Cooperation, has started conducting the engineering for the construction of off-site infrastructure valued at about $20-million in exchange for shares in TKGM.

Key Contracts and Suppliers
Ausdrill (mine services).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Kefi Minerals, tel +90 232 381 9431, fax +90 232 381 9071 or email info@kefi-minerals.com.

 

 

 

 

 

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.622s - 111pq - 2rq
Subscribe Now