Tocantinzinho gold project, Brazil – update

Image of gold ore

Photo by © Bloomberg

7th April 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Tocantinzinho gold project.

Location
Para state, Brazil.

Project Owner/s
G Mining Ventures Corp.

Project Description
The project has robust economics for a low-cost, large-scale, conventional openpit mining and milling operation, with industry-leading operating costs and a high rate of return.

The project outlines total gold production of 1.8-million gold ounces over 10.5 years, resulting in an average gold production profile of 174 700 oz/y.

The feasibility study project mine plan is based on proven and probable mineral reserves of 48.7-million tonnes at an average gold grade of 1.31 g/t for 2.04-million contained ounces of gold as of December 10, 2021.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $622-million and an after-tax internal rate of return of 24%, with a payback of 3.2 years.

Capital Expenditure
Initial capital costs are estimated at $458-million.

Planned Start/End Date
The project is construction-ready and first production is expected in the second half of 2024.

Latest Developments
G Mining Ventures has drawn down $91-million on its $250-million gold stream with Franco-Nevada.

The proceeds of the gold stream will be used to develop the Tocantinzinho project, currently under construction.

In connection with the draw on the gold stream, G Mining has provided evidence to Franco-Nevada that it has sufficient funding to fully satisfy the remaining project costs required to achieve commercial production and project completion.

In addition, G Mining has also closed, satisfied the conditions precedent, and started drawing on the previously announced $40-million equipment financing facility with Caterpillar Financial Services.

The project remains on track and on budget for commercial production in the second half of 2024.

Key Contracts and Suppliers
None stated.

Contact Details for Project Information
G Mining Ventures Corp, email info@gminingventures.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.047 0.923s - 111pq - 2rq
Subscribe Now