Tembang gold/silver project, Indonesia
Name and Location
Tembang gold/silver project, Sumatra, Indonesia.
Client
Sumatra Copper & Gold.
Project Description
The Tembang project has Joint Ore Reserves Committee-compliant proven reserves of 2.4-million tons at 2.5 g/t gold and 38.7 g/t silver for 200 000 oz of gold and three-million ounces of silver; and probable reserves of 3.1-million tons at 2.1 g/t of gold and 25.6 g/t of silver for a total of 200 000 oz of gold and 2.5-million ounces of silver.
The Stage 1 production plan is a low-cost, high-grade operation targeting a 400 000 t/y process capacity to produce 30 000 oz/y of gold and 200 000 oz/y of silver.
Stage 2 will increase throughput to 900 000 t/y and production to 50 000 oz/y of gold and 500 000 oz/y of silver.
The project has a 7.5-year mine life based on current resource inventory.
Value
$68.14-million.
Duration
Commercial production is expected in December 2013 quarter.
Latest Developments
Sumatra has received credit approval from Credit Suisse for $30-million in senior debt facilities to fund the commercial development of the Tembang project. The senior debt facilities are subject to the completion of project finance documentation and conditions precedent. These include final approval of the company’s forestry permit, expected in March, and the completion of the equity component of the funding package.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Sumatra Copper & Gold, tel +61 8 9389 2111, fax +61 8 9389 2199 or email info@sumatracoppergold.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation