Font size: - +

PERTH (miningweekly.com) – The advanced feasibility study into the Townsville Energy Chemicals Hub (TECH) base metals project, in Queensland, has confirmed the Stage 1 economics, prompting owner Queensland Pacific Metals (QPM) to start formal debt funding negotiations with potential lenders.

The Stage 1 TECH project is based on a nameplate capacity of 1.05-million-tonne-a-year throughput rate, with a ramp-up time of 2.25 years and a design life of 30 years. The Stage 1 project would produce 15 992 t/y of nickel sulfate, 1 746 t/y of cobalt sulfate, 607 395 t of hematite pellets, 4 000 t/y of aluminium and 28 856 t of magnesium oxide.

The advanced feasibility study estimated that the project would require a capital investment of A$2.1-billion, with the Stage 1 operation to have a post-tax net present value (NPV) of A$1.6-billion and an internal rate of return (IRR) of 15%.

The study estimated that the project would generate average revenue of $1.06-billion, at an operating cost of $515-million, and earnings before interest, taxes, depreciation and amortisation of $546-million.

“We are pleased to present the results of the feasibility studies for the TECH project. The outputs of these studies represent a moment in time and the culmination of hard work from the QPM team, Hatch and our other consultants. However, the work does not stop here as we now continue to work on the project and advance towards a final investment decision in parallel with our funding initiatives,” said MD and CEO Dr Stephen Grocott.

In addition to the feasibility study on the Stage 1 project, QPM has also undertaken a scoping study on the Stage 2 expansion of the TECH project, duplicating the Stage 1 operation.

The scoping study identified a number of synergies for the TECH project, including a A$350-million reduction in capital cost compared with the Stage 1 capital cost, as a result of synergies and no expansion of the high-purity alumina production, a near 7% reduction in operating costs based on economies of scale, increased purchasing power and shared services, and increased plant availability across the entire project.

The combined Stage 1 and Stage 2 operation is expected to produce 32 784 t/y of nickel sulfate, 3 579 t/y of cobalt sulfate, 1.24-million tonnes a year of hematite and 4 000 t/y of aluminium. The combined project would have an estimated post-tax NPV of A$3.3-billion and an IRR of 16.8%, generating revenues of A$2.1-billion.

First production from TECH is currently scheduled for the fourth quarter of 2024, and between now and a final investment decision, QPM will work with its equipment suppliers and engineering service providers to bring forward commissioning and first production.

Edited by Creamer Media Reporter

Comments

Showroom

John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

An unmanned breathalyser that is made to be tough and simple to use. Can be used in any environment for operator-free breathalyser testing.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.238 0.276s - 90pq - 2rq
Subscribe Now