Skouries gold/copper project, Greece – update

Image of Skouries project site

Photo by Eldorado Gold

14th April 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Skouries gold/copper project.

Location
Halkidiki peninsula, northern Greece.

Project Owner/s
Hellas Gold, a subsidiary of Eldorado Gold Corporation (95%), and Aktor (5%).

Project Description
The gold/copper porphyry deposit is planned to be mined using a combination of conventional openpit and underground mining techniques. The mineral process facilities will produce doré and a gold/copper concentrate.

The project has total proven and probable reserves of 157.67-million tonnes grading 0.74 g/t gold and 0.49% copper. 

Mineral resources have been estimated at 289.28-million tonnes grading 0.58 g/t gold and 0.43% copper, with inferred mineral resources of 170.14-million tonnes grading 0.31 g/t gold and 0.34% copper.

Gold production has been estimated at 140 000 oz/y. Average copper production is estimated at 67-million pounds.

Skouries has been designed as a two-phase operation.

Phase 1 comprises a combined openpit and underground mine operating over ten years.

Skouries will be a conventional truck-and-shovel operation. The mining sequence will consist of drilling, blasting and loading, as well as the hauling of ore and waste materials for processing and waste disposal.

Phase 1 total mill feed is eight-million tonnes a year consisting of a nominal 5.5-million tonnes a year from the openpit mine, combined with 2.5-million tonnes a year from the underground mine. 

At the start of the mine life, during the initial two-year underground mine ramp-up, the openpit feed rate is 6.4-million tonnes a year to maintain the eight-million-tonne-a-year mill feed. 

During Phase 1, about 6.5-million tonnes of oxide ore will be stockpiled, to be rehandled for mill feed during Phase 2. Phase 1 will be completed at the end of the openpit mine life in Year 10.

Phase 2 consists of underground mining for a further 13 years. Sublevel open stoping has been confirmed as the most appropriate underground mining method for the project.

Phase 2 mine production, from Year 11 to the end of the life-of-mine (LoM), will be provided from the underground mine. Phase 2 mine development begins in Year 4 to allow for a seamless ramp-up from the Phase 1 production of 2.4-million tonnes a year. During the first three years of Phase 2, the mill feed rate of eight-million tonnes a year will be maintained by reclaiming oxide ore stockpiled during Phase 1 at 1.6-million tonnes a year. 

From Year 14, Phase 2 mill feed will be maintained at an average of 6.2-million tonnes a year, solely from underground mine production.

The total LoM is 23 years.

The materials handling strategy for Phase 1 is based on truck haulage of run-of-mine ore directly to the surface from the loading bays using the dual ramp system.

Phase 2 materials handling will involve the shaft hoisting of ore to the surface. Shaft hoisting is critical to allow for ramp-up to full production of 6.4-million tonnes a year from the Phase 1 production of 2.5-million tonnes a year. 

To hoist the material by shaft, underground crushing will be implemented. The design of the Skouries mine includes provision for remote mining technology, which has an impact on the cycle times of stopes and the productivity of equipment. This technology includes the teleremote operation of mechanised equipment by an operator located on surface or in a remote area of the underground mine.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax estimated internal rate of return of 19%, with a payback of four years.

Capital Expenditure
Initial Phase 1 capital expenditure is estimated at $845-million.

Planned Start/End Date
Eldorado approved an investment decision and full restart of construction activities at Skouries in December 2022. Production is expected in the second half of 2025.

Latest Developments
Eldorado Gold has closed a €680-million project financing for the Skouries project, which is expected to cover 80% of the funding required, while the company will provide the remaining 20% to complete the half-built gold project.

Eldorado’s equity commitment for the project is backstopped by a €190-million letter of credit issued under its revolving credit facility.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Eldorado Gold manager – investor relations Peter Lekich, tel +1 604 687 4018 or email peter.lekich@eldoradogold.com; or director – communications and government relations Louise Burgess, tel +1 604 687 4018 or email louiseb@eldoradogold.com.

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Showroom

Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.154 0.215s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: