Sissingué gold project, Côte d'Ivoire
Name of the Project
Sissingué gold project.
Location
Côte d’Ivoire.
Client
Perseus Mining.
Project Description
The Sissingué project, including the nearby Belé East and West deposits, has total proven and probable reserves estimated at 5.9-million tonnes grading at 2.1 g/t gold.
Measured and indicated mineral resources for the project have been estimated at 15-million tonnes grading at 1.7 g/t gold.
A further 1.4-million tonnes of material grading 1.9 g/t gold is classified as inferred mineral resources.
The updated life-of-mine (LoM) plan envisages production of 358 000 oz of gold, including about 80 000 oz/y for the first 3.25 years of production, and about 70 000 oz/y over the full five-year mine life. This compares with envisaged production of 385 000 oz in the previous LoM.
The Sissingué plant will process a range of ore types – oxide, transition and primary porphyry, granite and sediment ores – with variable ore characteristics, gold grades and metallurgical treatment requirements.
The primary ores are significantly more competent than the oxide ores and require a longer leach time to optimise gold recovery.
Ores will be mined so that predominantly oxide/transition ore will be processed in two phases.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
Based on a total estimated construction cost of $107-million, the ungeared after-tax internal rate of return from the project has been estimated at 28%, with a payback of estimated at 39 months.
Value
Start-up capital costs are estimated at $107-million, including contingency.
Duration
First gold from Sissingué is expected in the March 2018 quarter.
Latest Developments
First gold from the Sissingué gold mine is expected by the end of January, ahead of schedule, with ramp up to full-scale commercial production expected to be achieved by March 31.
This follows the introduction of crushed ore to the mill and the carbon-in-leach plant.
The introduction of crushed ore to the mill is an important milestone in bringing Perseus’s second operating gold mine into production.
Key Contracts and Suppliers
Lycopodium (engineering, procurement and construction management contract).
On Budget and on Time?
The project is running on schedule and slightly under budget.
Contact Details for Project Information
Perseus Mining, tel +61 8 6144 1700, fax +61 8 6144 1799 or email info@perseusmining.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation