Name of the Project
Serra Sul +20 Mtpy project.

Location
In the municipality of Canaã dos Carajás, Brazil.

Project Owner/s
Brazilian miner Vale.

Project Description
The Serra Sul 120 entails increasing the S11D mine-plant capacity by 20-million tonnes a year.

The project involves expanding the yearly capacity of the S11D mine-plant by 20 million tons through initiatives such as developing new mining areas, installing a new semimobile crusher, duplicating the existing long-distance conveyor belt, and implementing new processing lines at the plant.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
$2.8-billion.

Planned Start/End Date
Commissioning is expected to start in the second half of 2026.

Latest Developments
Vale has received an operating licence for activities pertaining to the project, which it expects to "significantly increase" its iron-ore production capacity once completed. The licence was issued by Brazilian environmental agency Ibama.

In a securities filing, the company has said that the project is in line with its planned schedule.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Vale, email imprensa@vale.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
SafeQuip
SafeQuip

SafeQuip is a leading distributor and manufacturer of fire safety solutions, offering a comprehensive range of products designed to meet all...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.789s - 111pq - 2rq
Subscribe Now