Scotia zinc/lead project, Canada
Name of the Project
Scotia zinc/lead project.
Location
The project is located in Nova Scotia, Canada.
Project Owner/s
ScoZinc Mining.
Project Description
A prefeasibility study (PFS) has concluded that the project economics are very robust, with relatively low capital requirements and a short payback period.
The project is set to produce high-quality zinc and lead concentrates for more than 14 years, at low operating costs using conventional openpit mining methods, with a steady ore processing rate of 2 700 t/d.
The mine’s mineral resources will be extracted using conventional load-and-haul mining methods as determined by optimised pit designs and life-of-mine schedules.
The ScoZinc concentrator plant was last operated in 2009 at 2 200 t/d from the original nameplate design of 1 500 t/d using conventional crushing, grinding flotation, concentrate dewatering/drying, and rehandling loadout.
The PFS has confirmed that with relatively minor upgrades to the comminution, flotation and dewatering circuits, the plant can consistently operate at 2 700 t/d without major capital expansion.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $156-million and an internal rate of return of 52%, with a payback of 2.4 years.
Capital Expenditure
Preproduction capital expenditure is estimated at $30.8-million, including contingency of $2.7-million.
Planned Start/End Date
The PFS shows that commercial zinc and lead concentrate production can be achieved within 9 to 12 months.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
ScoZinc Mining, tel +1 902 482 4481 or email info@ScoZinc.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation