Sabina announces initial debt deal for Goose mine

30th August 2021

By: Creamer Media Reporter

     

Font size: - +

Project developer Sabina Gold & Silver on Monday announced an initial debt agreement for project financing for its Goose mine on its 100%-owned Back River gold project, in Nunavut.

The company has obtained a $20-million senior secured credit facility, which would enable it to fund critical path activities while pursuing full funding initiatives.

According to the Back River feasibility study, the project would require an estimated C$610-million for a mine that would produce 223 000 oz/y over 15 years.

Sabina said it had engaged in discussions with several streaming companies, which after due diligence have submitted stream proposals. The company stated that it was considering a proposal which, if completed, would reduce the equity requirements of project financing. 

“All of the work completed and planned so far provides the basis for a more executable project construction period.  We look forward to reporting progress on all fronts going forward,” said president and CEO Bruce McLeod.

The $20-million credit facility would be used to fund the construction of a ten-million-litre bulk fuel storage tank and containment at Goose, for procurement and delivery of bulk diesel fuel, for construction of fuel transfer systems at the Goose and port facility, for continued earthworks activities and for preparation of winter-ice-road construction and haulage in 2022.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.077 1.177s - 111pq - 2rq
Subscribe Now