R3bn Rustenburg commuter bus project advancing

12th April 2013

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

The Rustenburg Rapid Transport (RRT) project is gaining traction, with the local municipality having unveiled the design for Central station – the heart of the public transport system.

The first phase of the four-phase R3-billion RRT project kicked off last year with the construction of Corridor A, which linked Tlhabane to the central business district (CBD), and was set to progress further as construction on Corridor B and Central station started this year.

Phase 1 would encompass 45% of the entire project and was expected to be complete by the end of 2015, said RRT workstream manager for marketing and communications Sara Butchart.

The 24-month construction of the R150-million Central station, located in the Rustenburg city centre, was expected to start in October, while construction of Corridor B would start midyear.

The station would be the hub of public transport operations, with seven routes running through it, and would be linked to the existing taxi rank through Fatima Bhayat street.

Construction investment for all the other RRT Phase 1 stations was expected to reach R300-million.

Corridor B would link Boitekong, on the north-east of Rustenberg, to the CBD.

On completion of Phase 1, the RRT would deliver 225 000 passenger trips a day through 13 routes, 240 bus stops and 15 bus rapid transit stations, using 268 buses.

The project team was currently finalising the specifications for the buses and expected to go out on tender by midyear for the supply and assembly of the vehicles.

The full-service RRT, for which feasibility studies and initial plan- ning had been completed in 2010, would be completed by 2020 to service 500 000 commuters a day through 51 routes, using 854 buses.

Phase 2, which would be completed in the 2016/17 financial year, would link Kanana to Boitekong. Phase 3 would link Phokeng to Tlhabane by 2019/20, followed by the final Phase 4 roll-out to the rest of the region, including villages and rural areas.

Employees at the surrounding mines, accounting for 55% of all employment in Rustenburg, would be serviced through four dedicated routes on completion of the entire project.

Discussions were currently under way regarding the mines’ transport requirements and possible subsidies.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

SafeQuip
SafeQuip

SafeQuip is a leading distributor and manufacturer of fire safety solutions, offering a comprehensive range of products designed to meet all...

VISIT SHOWROOM 
Rosond
Rosond

ROSOND provides fast, efficient, safe, and cost-effective drilling and grouting services to mining and exploration industries throughout Africa.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.04 0.864s - 110pq - 2rq
Subscribe Now