Rustenburg BRT system to come on line in 2016

21st March 2014

By: Natalie Greve

Creamer Media Contributing Editor Online

  

Font size: - +

After experiencing several delays during the planning and design phase of the Rustenburg bus rapid transport (BRT) system in 2013, the Rustenburg local municipality (RLM) has reported that construction of the first phase of the public transport system had started, with operation targeted for the first half of 2016.

Thus far, R683-million has been spent on the system, dubbed Yarona, with R900-million allocated for 2014/15 and R1-billion budgeted for 2015/16.

The municipality noted at a stakeholder forum in March that construction of the first section of Corridor A along the R104 had started and would be extended to include additional taxi lay-bys and pedestrian paths. This section was due for completion at the end of March.

Construction of the bus lanes on the north-east Corridor B along the R510 is also under way with detours in place, while work will start later this year on the Central Station and the 13 BRT stations along the trunk route.

Bus stop and shelter designs are currently being finalised for the feeder routes, while work on the design for depot and bus holding areas will start later this year.

Some 305 bus stops are to be erected along the 13 Phase 1 routes and will generally be located on both sides of the road.

Meanwhile, as nine taxi associations have been identified as being affected by Phase 1 and 2 of the BRT system, the municipality has established a Taxi Negotiation Forum (TNF), comprising representatives from each association to negotiate compensation and the formation of a bus operating contract for former taxi drivers.

Further, a memorandum of understanding has been concluded between RLM and the affected Bojanala bus company, confirming the start of an engagement process between the parties.

“It is expected that this process will take another 12 months to complete,” RLM said.

According to the municipality, over 600 local jobs have been created during the initial phase of the projct, with the development of a labour registration database currently under way.

In addition, a labour project steering committee was formed to ensure that the labour recruitment was equitable across the local municipal wards, and that small, medium-sized and micro enterprise subcontractors were procured from those wards, where possible.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.728s - 110pq - 2rq
Subscribe Now