Rukwa coal-to-power project, Tanzania

14th December 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Rukwa coal-to-power project (RCPP).

Location
Tanzania.

Client
Edenville Energy.

Project Description
A feasibility study completed on the project has indicated an economically sound project with a 30-year, 120 MW coal-fired power plant. There is the possibility that the power plant could be scaled up to 300 MW.

The Rukwa coalfields comprise the Mkomolo, Namwele and Muze deposits.

The project hosts 173-million tons of measured and indicated coal, sufficient to support the station over the life of the project.

Output has been estimated at 10 000 t/m.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Independent power modelling consultancy Diamond Energy has completed a new financial model for Aim-listed Edenville Energy’s RCPP.

The new financial model builds on and validates the results and integrity of the financial model compiled from the results of the 2015 power plant feasibility study.

It has resulted in a 14% increase in the project’s pretax net present value to $252-million, from the previous estimate of $220-million, while the internal rate of return has improved to 23.4%, compared with 23.1% in the 2015 study.

Value
The capital expenditure to deliver a combined mine and 120 MW power plant is estimated at between $180-million and $200-million.

Duration
Not stated.

Latest Developments
Edenville Energy has resubmitted its tender qualification documents to the Tanzania Electricity Supply Company (Tanesco).

Edenville Energy has advised its shareholders that the resubmission and opening of the documents took place in front of other bidders, with Edenville’s documents officially accepted as complete and complying with Tanesco's requirements.

This formal process is the initial stage in the selection of projects to provide power for the Tanzanian electricity grid. 

Tanesco will assess the applications and select projects to advance to the next stage of the tender process. No defined time limits have been provided for the completion of the assessment.

Key Contracts and Suppliers
Not stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Edenville Energy, tel +44 20 7653 9850 or email info@edenville-energy.com.
 

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
SafeQuip
SafeQuip

SafeQuip is a leading distributor and manufacturer of fire safety solutions, offering a comprehensive range of products designed to meet all...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.052 0.732s - 111pq - 2rq
Subscribe Now