Round Mountain Phase W, US
Name of the Project
Round Mountain Phase W.
Location
The project is located in the US state of Nevada.
Client
Kinross Gold Corporation.
Project Description
The Round Mountain Phase W feasibility study envisages a layback of the current pit, construction of a new carbon-in-column (CIC) plant and heap-leach pad, and additions to the mining fleet and equipment, as well as the relocation of some existing infrastructure.
As a result of the Phase W feasibility study, estimated proven and probable mineral reserves at Round Mountain have increased from 1.3-million ounces of gold as at December 31, 2016, to 2.8-million ounces of gold.
Phase W is expected to add 1.5-million ounces of gold to the life-of-mine plan.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an incremental after-tax net present value, at a 5% discount rate, of $135-million and an internal rate of return of 13%.
Value
Initial plant and infrastructure capital costs are estimated at $230-million.
Duration
Stripping of Phase W ore is expected to begin in early 2018, pending the permitting process, which is proceeding on schedule.
Construction and relocation of infrastructure is expected to be completed by the second quarter of 2019, and initial low-grade Phase W ore to be encountered in mid-2019.
Latest Developments
With Phase W approved for development, procurement activities for long-lead items and mining equipment have started, along with advanced engineering. Additional state and federal permitting for the project is required, which is proceeding as planned.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Kinross Gold Corporation senior VP: investor relations and corporate development Tom Elliott, tel +1 416 365-3390 or
email tom.elliott@kinross.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation