Rio to cut 265 jobs at Rössing uranium mine, in Namibia
Rio Tinto Group will cut the workforce at its Rössing uranium site, in Namibia, by 23% as the world’s second-largest mining company responds to weaker demand for the metal used to fuel nuclear power plants.
Production will fall to “slightly less” than 2 000 metric tons in 2014 from 2 409 metric tons in 2013, says Rössing Uranium MD Werner Duvenhage. It will cut 265 of the 1 168 positions at the mine.
Rössing’s operations are suffering from lower grades and a slump in global demand for nuclear fuel, following Japan’s Fukushima reactor disaster in 2011. Namibia is the largest uranium producer after Kazakhstan, Canada and Australia. The cost-reduction measures will save as much as N$1-billion, says Duvenhage.
“We have to keep the company operating to avoid care and maintenance or complete closure,” he says. Starting next month, Rössing will reduce its operating cycle to five days a week from seven.
Rössing will maintain production levels, which will enable the company to satisfy long-term sales contracts, Duvenhage says. “We are significantly downgrading production targets.”
It is not the first time Rössing has reduced its workforce. It fired 276 workers in 2012 in response to weaker uranium prices. In March 2011, an earthquake and tsunami crippled Tokyo Electric Power Company’s Fukushima nuclear power plant, a disaster that led to Japan suspending its fleet of reactors.
Rössing plans to “ramp up production after 2017” and will likely return to full output in 2018 and 2019, says Duvenhage. “We have to undertake these measures to reposition the operation for the future as we still believe strongly in the future of uranium.”
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation