Rhyolite Ridge lithium/boron project, US

31st July 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Rhyolite Ridge lithium/boron project.

Location
Nevada, in the US.

Project Owner/s
ioneer.

Project Description
A definitive feasibility study (DFS), completed in April 2020, has placed Rhyolite Ridge as the single-most attractive project for the production of lithium carbonate, lithium hydroxide and boric acid globally.

The lithium and boron mineral resource is estimated at 146.5-million metric tonnes, including an ore reserve of 60-million metric tonnes, an increase in the reserve from the previous estimate of 280% over the 26-year life-of-mine (LoM).

The mine plan comprises almost entirely of reserve material, with nearly 50% of that being proven ore reserves.

The resource remains open in three directions, allowing for a potential extension to the life of the mine.

The project will mine 2.5-million metric tons a year of ore over the LoM to produce about 20 600 t/y of lithium carbonate or about 22 000 t/y of lithium hydroxide and 174 400 t/y of boric acid, on average, for the LoM.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% real discount rate, of $1.265-billion and an unlevered internal rate of return of 20.8%, with a payback of 5.2 years from the start of first production.

Capital Expenditure
The DFS estimates that the total capital expenditure to complete the project will be $785-million, including an 8% contingency.

This represents an increase of $186-million from the PFS.

Planned Start/End Date
The project schedule has a total duration of 41 months from the start of the engineering, pro­curement and construction management phase to final completion, with first product shipment expected in the second quarter of 2023.

Latest Developments
The DFS has recommended that the project continue to the execution engineering stage, and that funding of $785-million be obtained and approved for the implementation of the project.

Key Contracts and Suppliers
Fluor (DFS).

Contact Details for Project Information
ioneer, tel +61 2 9922 5800.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
14th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.141 0.194s - 91pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: