Quebrada Blanca Phase 2 project, Chile
Name of the Project
Quebrada Blanca Phase 2 (QB Phase 2) project.
Location
The project is located in northern Chile.
Client
Teck Resources.
Project Description
The proposed QB Phase 2 project will extend the life of the existing mine as a large-scale concentrate-producing operation. The project will have an initial mine life of 25 years.
The mine will include a 140 000 t/d concentrator and related facilities; a new port facility and desalination plant; and concentrate and desalinated water pipelines.
QB Phase 2 is expected to have a production capacity of more than 250 000 t/y of copper and 8 000 t of molybdenum in concentrate for the first ten years of mine life.
Jobs to be Created
Not stated.
Net Present Value/Internal Rate of Return
Not stated.
Value
Project optimisation work currently under way targets capital costs in the range $4.5-billion to $5-billion, with an initial mine life of 25 years, consistent with the capacity of the revised tailings facility that is located closer to the mine.
Duration
A decision to proceed with development is contingent on regulatory approvals and market conditions, among other considerations. Given the timeline of the regulatory process, such a decision is not expected before mid-2018.
Latest Developments
Teck Resources has, as part of the regulatory process, submitted the social- and environmental-impact assessment for the Quebrada Blanca Phase 2 project to the Tarapacá Environmental Authority.
The updated feasibility study, including capital and operating cost estimates for the project, is expected to be completed in the first quarter of 2017.
Key Contracts and Suppliers
Not stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Teck Resources VP investor relations and strategic analysis Greg Waller, tel +1 604 699 4014 or email greg.waller@teck.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation