PTM to update Waterberg DFS, launches initial works programme

20th October 2022

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

TSX- and NYSE-listed Platinum Group Metals (PTM) says the Waterberg joint venture (JV) it has with Impala Platinum holdings and other partners has approved an in-principle R380-million, or $21-million, pre-construction work programme.

The programme involves early infrastructure, de-risking and project optimisation, including initial road access, water supply, a first phase accommodation lodge, site construction power supply and advancement of the Waterberg social and labour plan.

An initial budget of R45-million, or $2.5-million, has been approved by the partners and will be spent by March 31, 2023.

PTM CEO Frank Hallam says the early works programme will significantly de-risk the future construction of the Waterberg palladium project, which is located in South Africa’s Limpopo province.

While the works programme is executed, PTM continues to seek a third-party concentrate offtake agreement for the Waterberg JV, and, depending on its outcome, PTM will assess the potential of establishing a new smelter and base metal refinery business, jointly with third-party investors, to further process the concentrate produced by the mine.

Meanwhile, PTM also plans to undertaken an update to the 2019 Waterberg definitive feasibility study (DFS), including a review of cut-off grades, mining methods, infrastructure plans, scheduling, concentrate offtake, dry stack tailings, costing and other potential revisions to the project’s financial model.

As a precursor to the DFS update, PTM plans to undertake an infill drilling programme near surface, which will cost about R23-million, or $1.2-million. The programme will comprise 32 boreholes and the material recovered will predominately be assayed, as well as tested for its ability to be dry-stacked.

Should it be possible to implement dry-stacked tailings, PTM says the mine’s water consumption can be reduced by between 40% and 50%.

Other partners of the JV are Japan Oil, Gas and Metals National Corporation, Hanwa, and Mnombo Wethu Consultants.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Projects

Image of gold nuggets
Bankan gold project, Guinea – update
Updated 2 hours 24 minutes ago By: Sheila Barradas

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.211 0.246s - 107pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: